So with that I'm going to turn on the recording.

00:00:00.000 --> 00:00:00.000
And with that, it is my pleasure to officially welcome you to today's internet seminar.

00:00:00.000 --> 00:00:00.000
Again, you should be joining us for the Federal Facilities Academy. This is the first webinar in a series of events.

00:00:00.000 --> 00:00:00.000
Today's topic will be land use and on-site off-site determinations. Now we'll talk more about the webinar series in just a moment for the whole academy, but before we get into that, I'd like to walk through a series of housekeeping items.

00:00:00.000 --> 00:00:00.000
My name is Gene Ballant. I'll be serving as the technical moderator for today's session joining you from EPS Technology Innovation in Field Services Division.

00:00:00.000 --> 00:00:00.000
In just a moment, I'll turn the floor over to your 3 presenters. Starting with any LIHA from EPA, federal facilities restoration and reuse office.

00:00:00.000 --> 00:00:00.000
But before I do that, as I said, let me walk through a few of these reminders to make sure that everybody understands how to participate.

00:00:00.000 --> 00:00:00.000
The first thing I'll do is just note that we do have a unique seminar homepage.

00:00:00.000 --> 00:00:00.000
The URL is shown in red on this slide that we have created for today's session on that seminar homepage.

00:00:00.000 --> 00:00:00.000
There are sections that will give you information about our speakers, about the session. There are links to download what's called the participant manual, which includes the slides and speaker notes.

00:00:00.000 --> 00:00:00.000
There are links to a series of related resources, a link to the flyer for the federal facilities academy.

00:00:00.000 --> 00:00:00.000
A whole bunch of good stuff is contained here on that seminar homepage. It's the same place you went when you signed up.

00:00:00.000 --> 00:00:00.000
It's the same place you went to check in for today's broadcast and it is the same place that I will point you to when our live event is done.

00:00:00.000 --> 00:00:00.000
So I encourage you to bookmark that URL and save it for reference. Now we're hosting today's broadcast live through Zoom.

00:00:00.000 --> 00:00:00.000
You can use the free Zoom application or through a browser of your choice. But if you have any issues with Zoom, please know we did post the materials and when you check in online through Clu and the last option you'll see post checking in will provide you the call in number.

00:00:00.000 --> 00:00:00.000
So if you need to, you can simply call in and listen by phone and follow along. Manually.

00:00:00.000 --> 00:00:00.000
But let us know if you have issues. We'll be more than happy to troubleshoot and try to get you on board for that full interactive delivery through Zoom.

00:00:00.000 --> 00:00:00.000
Audio is available online using your device or through telephone. Again, the audio controls are located in the lower left in Zoom.

00:00:00.000 --> 00:00:00.000
Regardless of how you listen, all participants are muted. That means there's no need to look for a mic icon.

00:00:00.000 --> 00:00:00.000
We have already taken care of that for you. I encourage you to check your local volume settings and adjust as needed but if you have problems with the audio try disconnecting from a VPN if you can and if that doesn't solve the problem send me a message in the Q&A and I'll be happy to troubleshoot and get you on board for a better broadcast.

00:00:00.000 --> 00:00:00.000
As noted, there is a few or there are several buttons at the bottom of your screen, but one of the most important ones is the Q&A button.

00:00:00.000 --> 00:00:00.000
So if you haven't done it yet, go ahead and click that QA button right now and I do mean you right now click it and a new window is going to open up.

00:00:00.000 --> 00:00:00.000
You can resize the Q&A window and place it somewhere on your screen for best viewing. That Q&A window is the primary way we'll be taking questions and comments from our audience.

00:00:00.000 --> 00:00:00.000
You can send questions and comments in or report take you to tech issues at any time there's no need to wait for a designated break and then we'll pause at various points in read questions out loud for the presenters to answer as time permits.

00:00:00.000 --> 00:00:00.000
So I encourage you to send in those questions as soon as they occur to you so we can build up a queue and get there as much as we can in the time that we have allotted today.

00:00:00.000 --> 00:00:00.000
As noted, closed captioning is available. Look for the CC or transcript button at the bottom.

00:00:00.000 --> 00:00:00.000
And then I will point out we are recording our session. I will provide instructions at the very end on how you'll be able to access that recording as well as share your feedback and then get a certificate for our session today.

00:00:00.000 --> 00:00:00.000
So stick with me until the very end because I'll walk through those reminders at the end. Just in case you're brand new to Zoom, if you're not familiar, remember those audio controls in the lower left of your screen, presentation materials will appear here in the main portion with speaker videos off to the side.

00:00:00.000 --> 00:00:00.000
But you have some view options in the upper right and upper center to adjust the size and scale of content that's being shown.

00:00:00.000 --> 00:00:02.000
And then as mentioned live close caption controls are in the bottom with that all important Q&A button where you can submit your questions and comments and report tech issues at any time.

00:00:02.000 --> 00:00:11.000
I think that's the end of the technical reminders that I have today. But, Emmy, did you want to go through a brief overview of the Academy before I call up your presentation materials.

00:00:11.000 --> 00:00:18.000
Sure, thank you, Jean. So for everyone who's joining us today, wanted to talk a little bit about the federal facilities academy.

00:00:18.000 --> 00:00:20.000
It is a voluntary training program developed for EPA's remedial project managers as well as project managers from other federal agencies.

00:00:20.000 --> 00:00:37.000
State and local government and tribal groups who work on federal facility cleanups at superfund sites. So we have 11 webinars that are part of our 2,024 offerings listed here.

00:00:37.000 --> 00:00:46.000
They're all open and available for registration so you can check them out at the website provided. And then there's also an in person 3 day course.

00:00:46.000 --> 00:00:58.000
I say in person occasionally we offer it virtually as well. Should you complete all 12 courses, you can receive a certificate of completion from our director of the federal facilities super fund program.

00:00:58.000 --> 00:01:04.000
And I'll let Gene explain how to show that you've received credit for each of these.

00:01:04.000 --> 00:01:12.000
Alright, thank you, Emmy. So let me go ahead and take us forward. This is one of the most common questions that I get is how do you get credit.

00:01:12.000 --> 00:01:19.000
So as I mean, there's a series of webinars that will be held online and then a classroom delivery to a limited audience.

00:01:19.000 --> 00:01:23.000
For the online webinars for those 11 classes that will be hosting here through Cluent, you can participate in any of them live online.

00:01:23.000 --> 00:01:33.000
Or replay the recorded versions of any of those sessions. For the in-person classroom training, the only way you can receive credit is to attend that one in person if you're part of the limited audience.

00:01:33.000 --> 00:01:43.000
Such as EPA states, tribes, and other federal agencies. Now, for each one of the clue and webinars, whether you attend it live or replay it, you can receive an individual certificate for each one of those sessions.

00:01:43.000 --> 00:02:00.000
We'll talk about how to get that credit at the end of each delivery, but essentially you'll share feedback, check a box when you submit your feedback, and then you'll immediately have access to a certificate for any of the 11 webinars that you attend live or replay online.

00:02:00.000 --> 00:02:03.000
And then as Emmy highlighted, if you're able to complete all of those webinars, either in all online, all archived or some combination of live and archived.

00:02:03.000 --> 00:02:17.000
Andrew also qualify and can attend the in person delivery, then you can receive that Academy certificate that recognizes your involvement in all parts of this series.

00:02:17.000 --> 00:02:23.000
So I think that's the end of that summary. And, I mean, if it's okay, I'm gonna go ahead and call up the presentation materials.

00:02:23.000 --> 00:02:27.000
I think it's about time to get started. So I'm going to turn the floor over to you.

00:02:27.000 --> 00:02:33.000
Oh, right. Thank you so much. So we're ready to start our first offering of our 2024 webinars.

00:02:33.000 --> 00:02:38.000
Which is on determining land use and onsite offsite determinations. My name is, and on-site off-site determinations.

00:02:38.000 --> 00:02:47.000
My name is Emilia. I am the deputy director of our federal facilities restoration and reuse office here at EPA headquarters and we have some other instructors joining us.

00:02:47.000 --> 00:02:58.000
I'll allow them to introduce themselves when it's their turn to speak. So we'll just start with a course overview where we have 3 different sections we'll be covering.

00:02:58.000 --> 00:03:03.000
The first one will be on land use and EPA guidance on how to determine land use will transition to site reuse, talking about beneficial.

00:03:03.000 --> 00:03:13.000
Reuse and reuse assessment, specifically guidance on those topics. And then we'll finish out with our on-site off-site determinations.

00:03:13.000 --> 00:03:20.000
That'll take on the role of permit requirements and the off-site rule. So let's go ahead and jump into it.

00:03:20.000 --> 00:03:21.000
When it comes to determining land use, there are a number of things that need to be considered, right?

00:03:21.000 --> 00:03:37.000
Those land use assumptions that are being made are going to identify what exposure pathways are considered. How are they evaluated for current risk assessments and future potential threats?

00:03:37.000 --> 00:03:49.000
So if you're looking at a recreational land use in the future post cleanup, what kind of exposures do you have to look at or people on the site for so many hours per day.

00:03:49.000 --> 00:03:57.000
We have young children, pregnant mothers who are the most vulnerable populations that might be using that land.

00:03:57.000 --> 00:04:13.000
So recreational scenarios are going to be different from agricultural ones where you might be more particularly interested in that exposure pathway of water percolating through the soil and particularly being picked up by vegetation versus industrial and residential.

00:04:13.000 --> 00:04:23.000
So all of those are important to know in the beginning because our remedial action objectives goals for cleanup will be dependent on those land use assumptions.

00:04:23.000 --> 00:04:32.000
So it is very much. Something that has to be considered throughout the cleanup process.

00:04:32.000 --> 00:04:39.000
So before we get into too much more lecturing, we're go, we have a few polls for interaction and Gene, will you take us through these?

00:04:39.000 --> 00:04:47.000
Absolutely. So I mean, I'm going to go ahead and call up our first poll. There should be a new pop-up window that is on the screen for the audience asking a question.

00:04:47.000 --> 00:04:53.000
When selecting a circle of remedy at a federal facility, who determines the reasonably anticipated land use?

00:04:53.000 --> 00:05:00.000
Is it A, EPA, B, the lead cleanup agency, see the state, D the public or E, all of the above.

00:05:00.000 --> 00:05:07.000
So I'll have you read through those responses and then simply click the circle to the left of the response that you think is correct and then press the submit button.

00:05:07.000 --> 00:05:12.000
If you don't see the pop-up poll, look under a 3 dots or more menu.

00:05:12.000 --> 00:05:17.000
You may see it buried there. And of course, if you don't see the poll window actually displaying, that's okay.

00:05:17.000 --> 00:05:31.000
You can share your responses by sending a message into the Q&A. And as I'm looking, it looks like about 60% of the audience have shared their responses and I promise you we won't be grading you so it's okay take your best guests and submit those answers.

00:05:31.000 --> 00:05:38.000
And I think I'll go ahead and close the pull down here in 3. 2 one and let's take a look.

00:05:38.000 --> 00:05:40.000
All right, I mean, we've got a bit of a distribution, although 60% of the audience picked E, all of the above.

00:05:40.000 --> 00:05:50.000
A pretty significant portion of them thought perhaps it was the lead cleanup agency or even EPA. What's the right answer?

00:05:50.000 --> 00:06:06.000
So the right answer is that no single party or group should be determining land use. On their own. It really is a discussion that needs to happen between your regulatory agencies, the lead cleanup agency, and interactions with local state governments, the public on what the anticipated land use are reasonably anticipated land use may be for that area.

00:06:06.000 --> 00:06:27.000
Especially if you have sites that are located near cities or growing populations. There it's likely going to be more public interest in those types of situations or if you have an area around a superfund site that's been identified as a monument or wilderness area.

00:06:27.000 --> 00:06:39.000
Again, recreational activities there are going to be of interest to the public. So we'll talk more about the guidance that lays out which partners should be part of that conversation, but no, it's not just a single group.

00:06:39.000 --> 00:06:49.000
Or agencies decision on what that will be.

00:06:49.000 --> 00:06:50.000
Yeah.

00:06:50.000 --> 00:06:51.000
Alright, we have another poll. So I'm gonna go ahead and launch our next question here. And this time the new poll window should be asking a second question.

00:06:51.000 --> 00:06:57.000
Can the land use determination add a federal facility change. You'll have 3 choices. A, yes, B, no, or C. Never.

00:06:57.000 --> 00:07:10.000
Again, same instructions. Click the circle to the left of the answer that you think is correct. And then hit that submit button.

00:07:10.000 --> 00:07:17.000
Now in this case, almost 70% of you have voted and the audience is pretty consistent that I can see in the answer that they are picking right now.

00:07:17.000 --> 00:07:21.000
So I think I'm gonna close this one down because we've got group consensus. Here in 3, 2, one, and let's share those results.

00:07:21.000 --> 00:07:31.000
So almost everyone said A. Yes, it can change. What's the right answer?

00:07:31.000 --> 00:07:39.000
Yes, definitely yes, it can change and in the event that the land use does change say it was anticipated to be a recreational area but now years later they're looking at developing it for residential purposes or commercial purposes.

00:07:39.000 --> 00:07:49.000
If that land use changes, then it's important to go back and evaluate all the implications that may have.

00:07:49.000 --> 00:07:59.000
For example, what was the selected remedy? Does is that remedy still protective given there are different exposure pathways that need to be considered with this updated land use.

00:07:59.000 --> 00:08:16.000
So looking back at the protectiveness of the remedy and how that's going to impact the land use long term is very important and we'll talk a little bit more about that in this webinar.

00:08:16.000 --> 00:08:25.000
So we'll go ahead and continue on to our next slide here with continuing on online. Use determinations.

00:08:25.000 --> 00:08:32.000
So again, I mentioned already that it's important to the process, the clean up process because how you're going to use the land after cleanup is going to help determine what your cleanup goals are.

00:08:32.000 --> 00:08:41.000
Those remedial action objectives. That in turn is going to affect the technologies that are considered and all the remedy components that are considered.

00:08:41.000 --> 00:08:56.000
Ultimately impacting the selected remedy. So having that land use discussion upfront is very important to the process and no it's not just .

00:08:56.000 --> 00:09:08.000
The lead agency or regulatory agencies to make this decision but often community involvement has a critical role in having those discussions with the community on what is reasonable for that land use looking into the future.

00:09:08.000 --> 00:09:17.000
And note that these discussions, these agreements should all be documented in the administrative record. Often your sometimes will have a land use plan that can be referenced.

00:09:17.000 --> 00:09:24.000
Hopefully that's a not just issued by one agency, unilaterally, but actually reflects.

00:09:24.000 --> 00:09:34.000
A group process where regulatory agencies Other interested parties are involved in the conversation. But again, that should be in your administrative record.

00:09:34.000 --> 00:09:48.000
So there's a way to track what conversation was had and the decision that came from that.

00:09:48.000 --> 00:09:53.000
A few things I wanna highlight for the group are pieces of EPA guidance that are handy to have PDF downloaded on your computer for easy reference.

00:09:53.000 --> 00:10:13.000
The top 3 for land use I would say is the 1995 land use in the circle of remedy selection process guidance and keep in mind that there should be links to all of these popping up in the chat as well as on the web page that has all the course resources.

00:10:13.000 --> 00:10:21.000
Also there's the 2,001 reuse assessments, a tool to implement the superfund land use directive. Also very helpful.

00:10:21.000 --> 00:10:27.000
And lastly, the considering reasonably anticipated future land use and reducing barriers to reuse at EPA led superficial sites.

00:10:27.000 --> 00:10:39.000
Granted that it specifically says EPA led, but the information in there is still very helpful. At federal facility sites as well.

00:10:39.000 --> 00:10:44.000
A lot of information you can consider.

00:10:44.000 --> 00:10:48.000
So let's go ahead and start with the first land use directive of guidance. That's from 1995.

00:10:48.000 --> 00:10:55.000
So yes, it's been a few years. But we still point to this guidance and the important information that it has.

00:10:55.000 --> 00:11:17.000
So it lays out having discussions with local land use planning authorities, local officials, and the public really should be conducted as early as possible during the initial scoping phase of the remedial investigation and feasibility study or the RIFS.

00:11:17.000 --> 00:11:24.000
For federal facility sites, the unique part is that many of our sites may have been placed on the national priorities list.

00:11:24.000 --> 00:11:32.000
1020 years ago. So cleanup has been in process for a long time. These conversations might have taken place.

00:11:32.000 --> 00:11:42.000
20 plus years ago. For some of our newer, I think we've added like 6 federal facility sites to the national priorities list and the last couple of years.

00:11:42.000 --> 00:11:55.000
Ideally, when those processes are just starting, then you can have that conversation. But again, the point here is having that discussion very early in the process, be it by having public meetings.

00:11:55.000 --> 00:12:00.000
Or other workshops, other types of events where you can speak with community members should be conducted and that information taken and considered when looking at land use.

00:12:00.000 --> 00:12:08.000
Other things you might consider are zoning laws. Or public population growth patterns, what's going on with the national resources in that area.

00:12:08.000 --> 00:12:36.000
The need for institutional controls, all of that should be considered. In those discussions early on. And then as I had already mentioned, whatever considerations of anticipated future land use are made, that should be documented in the administrative record because 1020 years later, who's gonna be around that still remembers that discussion?

00:12:36.000 --> 00:12:47.000
There might be a few people because we do have long tigers on some of our cleanups, but having that record is really, really important.

00:12:47.000 --> 00:12:52.000
The directive also says that in for future land use assumptions are going to help with the baseline risk assessment and feasibility study.

00:12:52.000 --> 00:13:04.000
So it's focusing on developing practical, practicable, that word always gets me and cost-effective remedial alternatives.

00:13:04.000 --> 00:13:05.000
That's also going to help with the available land use types following completion of the remedial action.

00:13:05.000 --> 00:13:16.000
So you know your cleanup is going to support the plan, the vision for the site long term. After clean up.

00:13:16.000 --> 00:13:24.000
Cause we want to complete cleanup at our federal facility site.

00:13:24.000 --> 00:13:31.000
One cool example we wanted to share with you all was the NASA Jet Propulsion Laboratory or JPL.

00:13:31.000 --> 00:13:32.000
So for this site, the primary land use in the surrounding area around the site was residential and like commercial.

00:13:32.000 --> 00:13:50.000
So when they did their based on risk assessment, they evaluated a hypothetical on facility resident, a commercial worker and an instructor, a construction worker.

00:13:50.000 --> 00:14:00.000
So again, based on the land use they could see of the surrounding area. Going into the RFS, particularly the baseline risk assessment, they considered those scenarios so they had the appropriate exposure pathways being considered.

00:14:00.000 --> 00:14:12.000
And even though NASA had no intent to use the site for residential purposes anytime in the foreseeable future by having a human health risk assessment that included of that hypothetical residential use scenario.

00:14:12.000 --> 00:14:28.000
It really provided a book end on the most conservative and protective results they could have when going forward and selecting their remedy.

00:14:28.000 --> 00:14:34.000
So you may have a more conservative.

00:14:34.000 --> 00:14:42.000
Land use scenario that you're using through the circular process, but that is just to support what may be a reasonably anticipated.

00:14:42.000 --> 00:14:58.000
Future land use. So here they went that extra step I would say to be able to So, We know that what we're doing here is safe and that it supports any reasonable land use that may occur.

00:14:58.000 --> 00:15:02.000
Okay.

00:15:02.000 --> 00:15:16.000
Finishing up on this piece of EPA guidance. Keep in mind that remediation objectives should be developed in order to develop those alternatives that would are going to get you to the cleanup you need those cleanup levels associated with that reasonably anticipated future land use over as much of the site as possible.

00:15:16.000 --> 00:15:29.000
Granted, some that are facility sites are very large and it might not have this same land use assumption across hundreds of square miles.

00:15:29.000 --> 00:15:42.000
They're not all that large, but many of them are. Some areas may be recreational or industrial depending on what's happening at the site.

00:15:42.000 --> 00:15:51.000
So again, you want to be able to have those video action objectives that are going to support the long term cleanup.

00:15:51.000 --> 00:15:58.000
In cases where the future land use is relatively certain of the remedial action objectives generally should reflect this in land use.

00:15:58.000 --> 00:16:07.000
For example, if you have a landfill site, it's highly likely that the future land use will remain unchanged from a long term waste management area.

00:16:07.000 --> 00:16:17.000
That landfill is gonna be there essentially in perpetuity. You're not anticipating that there would be major changes to the land use there.

00:16:17.000 --> 00:16:24.000
That's just a simple example, but we have a couple of case studies that we'll share with you.

00:16:24.000 --> 00:16:31.000
So now I'd like to hand it over to Jill to introduce herself and talk to us about her use.

00:16:31.000 --> 00:16:39.000
Thank you, Emmy. My name is, and I also work in EPAs Federal Facility Restoration and Reuse Office.

00:16:39.000 --> 00:16:45.000
And we'll get ready to it. We'll talk about site reuse. It's one of my favorite topics in the Super Fun program.

00:16:45.000 --> 00:16:51.000
These examples on the screen are winners of the National Feder Facilities Excellence in Site Reuse Award.

00:16:51.000 --> 00:16:56.000
We created this awards of celebrate all the great clean up and renew this work that occurs at federal facility sites.

00:16:56.000 --> 00:17:06.000
This border highlights redevelopment successes and recognizes sites for the tight clean up and reuse and greatly benefit local communities around the country.

00:17:06.000 --> 00:17:08.000
These sites can also be used as models for your, cleanup work. And so I highly encourage you to take a look at them.

00:17:08.000 --> 00:17:17.000
Because they have a tremendous for use, examples.

00:17:17.000 --> 00:17:31.000
The common denominator of all these winners, there are 22 and counting, that it takes a team as Emmy mentioned to achieve positive for youth results, including start partnerships and a collaboration vision shared by the community, other fellow agencies, tribes, states, territories, local partners, politicians, developers, etc.

00:17:31.000 --> 00:17:51.000
They're different for every site, but those are a common theme. If you would like more information about the National National Federal Facilities, Excellence Insight Res Award, there will be a link dropped into the chat.

00:17:51.000 --> 00:18:04.000
On the screen, some examples include the former ring court air station, El Toro. El Toro was decommissioned as an active base in 1,999 under the base free alignment and closure act.

00:18:04.000 --> 00:18:12.000
We will discuss base closures later in this presentation. Before the site was decommissioned, the nearly 5,000 acre site supported the fleet green forces in the Pacific Ocean.

00:18:12.000 --> 00:18:22.000
7 as a major West Coast jet. Fighter facility. Environmental Pax for the result of chlorinated solvent releases associated with a historical onsite station aircraft and vehicle maintenance activities.

00:18:22.000 --> 00:18:36.000
Extensive clean up efforts have facilitated transformation of approximately 1,300 acres of the site. So that the entire site, but a big portion of it.

00:18:36.000 --> 00:18:48.000
In 2,001 Orange County voters passed a measure authorizing the stations redevelopment as a park in a preserve for mixed public and private use, which resulted in the development of the Greg Park.

00:18:48.000 --> 00:18:53.000
If you have a chance, I would highly recommend you look it up. It's a very impressive clean up.

00:18:53.000 --> 00:19:02.000
It's a recreational destination that includes parks, playgrounds, hiking trails, multi-use facilities, and art complex, amphitheater, of police fire.

00:19:02.000 --> 00:19:11.000
Fire training facility and an indoor ice rink which serves as the training facility for national hockey lakes and a high in duck franchise.

00:19:11.000 --> 00:19:27.000
This for you's approach demonstrates how successful partnerships between public and private entities and the local community can facilitate the transformation of a military facility with certificate environmental issues into a multi-use area that is an asset to the community.

00:19:27.000 --> 00:19:38.000
And on the top of right hand side, there's the N or the naval industrial reserve ordinance plant also known as diarrhea.

00:19:38.000 --> 00:19:40.000
The Naval Industrial Reserve Ordnance Plant, also known as DIRECT.

00:19:40.000 --> 00:19:46.000
NYRAP puts an 80 acre super fun site where industrial activities including the production of naval guns during World War 2, contaminated soil and the groundwater.

00:19:46.000 --> 00:19:52.000
After clean up a developer purchase part of the site and the surrounding property and redeveloped it into the northern.

00:19:52.000 --> 00:20:05.000
Industrial Park. Today the park is home to multiple businesses including a brewery and these businesses employ over 1,100 people and generate an estimated 600 million in annual revenue.

00:20:05.000 --> 00:20:15.000
Okay. This for you development showcases the community benefits that could come from the reuse of vacant properties including reducing blight and generating tax revenue.

00:20:15.000 --> 00:20:21.000
So, before NYRAP was redeveloped, it was pre developed after, If the property was, remained vacant as well as surrounding property.

00:20:21.000 --> 00:20:33.000
So the redevelopment of this site was a big asset to the community.

00:20:33.000 --> 00:20:42.000
We'll move on to talk about the economic analysis and inventory of redeveloping federal facility super fund sites.

00:20:42.000 --> 00:20:52.000
As can see from the previous slides, federal facilities, super fun sites are being cleaned up across the country, helping communities reclaim and reuse thousands of acres of form of the contaminated land.

00:20:52.000 --> 00:20:59.000
Many sites are now host of parks, businesses, renewable energy facilities, wildlife habitat, neighborhoods, and farms.

00:20:59.000 --> 00:21:07.000
Our office tracks these sites from year to year to give a general overview of the beneficial effects associated with cleaning these sites up.

00:21:07.000 --> 00:21:21.000
We collect information about the number of businesses located on a site, the number of people employed at the businesses, annual employment income from Unsite jobs and annual sales revenue generated by businesses on site.

00:21:21.000 --> 00:21:30.000
The federal facility, Super Fund Reuse Data is remarkable. It's just, it's off the charts it's It has so much for you's potential.

00:21:30.000 --> 00:21:49.000
And 2023 the economic analysis of 91 of our federal facilities super fun sites identified more than 2,700 businesses and generated nearly 29 billion in annual sales provided more than 600,000 jobs and 60 billion in estimated annual employment income.

00:21:49.000 --> 00:21:56.000
And addition, we embarked on an inventory study, from 2,021 to 2,023.

00:21:56.000 --> 00:22:04.000
We tracked nearly 6,300 per use instances across a hundred 8 federal facility superfront sites.

00:22:04.000 --> 00:22:16.000
Of these sites, all of them were in for use or continued use. As you can see from the summary, the most, The largest type of reuses are commercial and ecological.

00:22:16.000 --> 00:22:38.000
I also want to point out that there are 39 seats. Sites with alternative energy reuses. If you would like more information on this economic redevelopment data, including, site snapshots, please visit our economic redevelopment website that will be in the chat.

00:22:38.000 --> 00:22:46.000
Now let's take a closer look at one of the alternative energy sites. Plants in Texas.

00:22:46.000 --> 00:22:55.000
Jee, would you please, queue the video?

00:22:55.000 --> 00:23:04.000
Sorry, bear with me one moment. Pull that video up here.

00:23:04.000 --> 00:23:11.000
This part of the nation has always been known for its ability to produce energy with oil being a major part of the economy.

00:23:11.000 --> 00:23:17.000
Currently though, just about everywhere you look, oil derricks are being overshadowed by wind turbines.

00:23:17.000 --> 00:23:30.000
According to the National Renewable Energy Laboratory, the latest figures show Texas is the biggest producer of wind energy with more than 15% of the state's generation originating in the skies above.

00:23:30.000 --> 00:23:38.000
Currently, it's estimated there are about 11,000 Lone Star Turbines and 5 of the tallest can be found across the street from the Pantex plant.

00:23:38.000 --> 00:23:42.000
A few years ago, the federal government mandated that by 2,020, renewable energy would account for 20% of the power needs for its facilities.

00:23:42.000 --> 00:23:56.000
About 2,009 they started doing alternative studies. We had a requirement of federal requirement that was supposed to go in effect in 2,020 to have 20% of our energy provided by a renewable source.

00:23:56.000 --> 00:24:01.000
And so we started working on it about 2,009 doing some trade-off studies. Mostly it came down between solar.

00:24:01.000 --> 00:24:07.000
And wind energy. And we decided on wind energy. It was the most cost-effective for our location at the time.

00:24:07.000 --> 00:24:13.000
That government backed pilot program, the Pantex Renewable Energy Project, or PREP, is considered a success.

00:24:13.000 --> 00:24:22.000
Within the first few months of production, the turbines towering 400 feet above the ground were creating the equivalency of about 60% of the electrical deeds of Pantax.

00:24:22.000 --> 00:24:27.000
I think it's immensely successful. It's the first of its kind for the DOE to do a behind-the-meter wind application where we tired the wind generation directly to plant load.

00:24:27.000 --> 00:24:45.000
Basically, we proved the engineering here works and then for viability anywhere else it's just economics of whether their rates at that site justify the cost savings to do in the project.

00:24:45.000 --> 00:24:56.000
The renewable side also posts some impressive numbers. Check this out. Generating more than 43 million kilowatt hours of electricity is equal to the power consumption of 3,800 homes.

00:24:56.000 --> 00:25:05.000
Conversely, the carbon footprint has diminished dramatically equal to removing 7,800 cars from the roads or planning 920,000 trees.

00:25:05.000 --> 00:25:13.000
All this with a combined cost savings of 2.8 million dollars annually. It's a viable source of renewable energy.

00:25:13.000 --> 00:25:21.000
In the panhandle, the Midwest, we proved that you can put it behind the meter application, then it just becomes the economics of.

00:25:21.000 --> 00:25:29.000
The tariffs that you're under and the rates you have to pay. Renewable wind energy is now a permanent part of the high plains landscape with turbines stretching from border to border.

00:25:29.000 --> 00:25:35.000
It's also home to the federal government's pilot program to use renewable energy sources at its facility, namely Pantex.

00:25:35.000 --> 00:25:55.000
But the first DUE facility to have renewable energy and we know we're by far the greatest generator because we're generate about 60% of our energy needs and nobody else is even close to that.

00:25:55.000 --> 00:26:03.000
Thank you. That was definitely an impressive reuse example. I also want to, talk about the report in America's landed initiative.

00:26:03.000 --> 00:26:15.000
So sister office that encourages renewable energy development. If you have a site that you want are considering renewable energy, I would, I would recommend contacting this office.

00:26:15.000 --> 00:26:18.000
They also have the re power in Mapper, which is a tool that provides information on renewable energy.

00:26:18.000 --> 00:26:27.000
Potential for contaminated sites and that link will be dropped in the chat as well.

00:26:27.000 --> 00:26:36.000
It's like about the reuse assessments. . S. Assessment is a tool to develop reasonable, anticipated future land use assumptions.

00:26:36.000 --> 00:26:49.000
The 22,001 reuse assessments a tool to implement the super fun land use directive or I'll call it the super fun line you're directive that any previously discussed and shared.

00:26:49.000 --> 00:26:55.000
Promotes early discussions with the community and other interested parties. Regarding potential future land use.

00:26:55.000 --> 00:27:03.000
Options for sites and promote the use of that information to develop realistic assumptions that are integrated into the response actions.

00:27:03.000 --> 00:27:11.000
This is an important step toward facilitate the reuse of sites following. They bring this assessment involves collecting and evaluating information to develop assumptions about reasonably anticipated future land uses at superficial sites.

00:27:11.000 --> 00:27:25.000
The scope and level of detail, the re assessments to be site specific and tailored to the complexity of the site.

00:27:25.000 --> 00:27:35.000
The extent of the contamination, the level of redevelopment activity that has already occurred at the site and that in in the density of development in the vicinity of the site.

00:27:35.000 --> 00:27:46.000
It should be known that reuse assessment should not have. It's the greatest, wait, the reuse assessment should have greatest applicability to sites with waste materials on the surface.

00:27:46.000 --> 00:27:53.000
And or contaminant soil. Teacher, groundwater use was that extensively considered in the super fun land use directive.

00:27:53.000 --> 00:28:03.000
There are separate expectations established in the NCP. The state EPA expects to return usable ground waters to their beneficial uses, for ever practical.

00:28:03.000 --> 00:28:09.000
Within a timeframe and that. That is reasonable. You given in a particular circumstances of the site.

00:28:09.000 --> 00:28:20.000
Stating that. A lot of these reuses do have, brown water. Treatments in place and the sites can be reused.

00:28:20.000 --> 00:28:33.000
Anyhow, in conjunction with the groundwater treatment. We'll see example that, as we move forward.

00:28:33.000 --> 00:28:45.000
To the reuse assessment. As we see at federal facility super fun sites for another federal agency or OFA is performing a circular base, remedial action or not time critical removal.

00:28:45.000 --> 00:28:55.000
The OLF should develop assumptions of reasonably anticipated future land uses as part of the response process consistent with the super fun land use directive.

00:28:55.000 --> 00:29:06.000
The 2,001 line use directive maintains contains an outline for the reuse assessment. I highly recommend that you reference this if you're developing a reuse assessment.

00:29:06.000 --> 00:29:15.000
It identifies the stakeholders, for example, site owners. Developers, state, local, and tribal governments, community members, for.

00:29:15.000 --> 00:29:22.000
Site description, environmental conditions such as contaminants, potential restrictions, wetlands, etc.

00:29:22.000 --> 00:29:24.000
Site ownership, and use considerations such as zoning, site master plans, institutional controls, historical and cultural resources.

00:29:24.000 --> 00:29:39.000
Community input, public initiatives such infrastructure plans and funds available. etc.

00:29:39.000 --> 00:29:50.000
Information obtained from the reuse assessment can be useful during the planning stages of the response action, including the baseline risk assessments when estimating potential future risk.

00:29:50.000 --> 00:30:03.000
The development of removal action objectives or RAOs in the development and evaluation of response alternatives and the selection of appropriate response action required for the protection of human health and the environment.

00:30:03.000 --> 00:30:19.000
Since better facility sites are often encompass thousands of acres with buildings, roads and other infrastructure, they're effective and efficient, clean up and reuse can play a pivotal role in a community's economic growth in neighborhood revitalization and makes them great candidates for site reuse.

00:30:19.000 --> 00:30:25.000
Large sites are sites with many favorable units and potentially different future use. Scenarios may benefit from multiple reuse assessments.

00:30:25.000 --> 00:30:48.000
Well, reuse assessment may not be necessary at every site or OU, the lead agency or OFA should collect and summarize available information about potential future uses for MPL sites and not time critical removal actions to form the basis for the future of the latest assumptions.

00:30:48.000 --> 00:30:55.000
I'd like to draw your attention to the super fun, redevelop it. Redevelopment mapper that will be dropped into the chat.

00:30:55.000 --> 00:31:14.000
This is another web based tool that explores potential for use opportunities. It highlights the site features and strong in areas to explore more information about the communities including infrastructure, income levels, unemployment numbers and land features.

00:31:14.000 --> 00:31:27.000
Alright, let's go to another example. This is one of my favorite examples. I actually was an intern at Fernal Preserve in the late nineties and it has come a long way since then.

00:31:27.000 --> 00:31:38.000
But, for now, formerly called the Feet Material Production Center as a former US Department of Energy uranium processing facility in rural Southwest Ohio.

00:31:38.000 --> 00:31:53.000
Real actions have addressed contamination at the site and long term groundwater cleanup is underway. The renewed process at this site engage community members and federal and state agencies in a process that integrated the media planning and future land use considerations.

00:31:53.000 --> 00:32:02.000
Ecological restoration was envisioned by the community, which advocated for mediation to an undeveloped park with an emphasis on wildlife.

00:32:02.000 --> 00:32:13.000
Components of ecological restoration were incorporated into the design plan for the site remedy. For now, has create examples of how the Reed's vision was incorporated into the remedy.

00:32:13.000 --> 00:32:20.000
As evidence by the Mesa, Prairie community planted on an onsite disposal facility cap.

00:32:20.000 --> 00:32:27.000
The use of the native vegetation also had a more practical benefit. The perennial bunch grasses and forbes that make up the.

00:32:27.000 --> 00:32:34.000
Tallgrass prairies are very hardy, grow in YouTube, poor conditions, our drought tolerant, discourages.

00:32:34.000 --> 00:32:42.000
Establishment of invasive meat species and prevent erosion of contaminated of prevent emotion of remediate areas.

00:32:42.000 --> 00:32:53.000
These features make native grasslands and an ideal cap for the on site disposal facility and for stabilization of highly disturbed.

00:32:53.000 --> 00:33:05.000
The infrastructure designed to support the public use of the site also incorporates several other features, a concrete pad that's support of your, activities is now the Visitor Center's parking lot.

00:33:05.000 --> 00:33:12.000
Former maintenance and access roads were incorporated into trail design. A stormwater sediment basin is now a bio treatment wetland that handles waste water from the visitor center.

00:33:12.000 --> 00:33:22.000
Renewable energy generated by a geothermal system is used to heat and cool the visitor center.

00:33:22.000 --> 00:33:30.000
This heated and cooling infrastructure is located in on-site pond that was left as a result of but of remediation.

00:33:30.000 --> 00:33:38.000
In addition, the renewable solar energy is used to power lights and gates across the spikes.

00:33:38.000 --> 00:33:53.000
This innovative, it cost effective cleanup transformed a contaminated site into a publicly accessible ecological preserve of 140 acres of wetlands, 350 acres of prairies, 400 acres of forest, hiking trails and a visitor center.

00:33:53.000 --> 00:34:02.000
It's now a community asset. The Fernel Preserve Foster's wildlife habitat and provides educational opportunities through environmental stewardship.

00:34:02.000 --> 00:34:09.000
This site was also a recipient of the 2019 national federal facilities excellence in site reuse award.

00:34:09.000 --> 00:34:16.000
The fact she can be seen. The link is in the chat.

00:34:16.000 --> 00:34:19.000
Alright, let's get back to the guidance. We'll discuss the 2010 directive.

00:34:19.000 --> 00:34:30.000
Considering reasonably anticipated future lab use and reducing barriers to reuse at EPA. LEDs to refund sites.

00:34:30.000 --> 00:34:35.000
It's also referred to as the reuse directive.

00:34:35.000 --> 00:34:39.000
Feature land use assumptions or designations, May change at any stage of the circular response process as we discussed during the poll.

00:34:39.000 --> 00:35:00.000
If it happens before broad signature, before the record of decision is signed, The lead federal agency, and EPA, determine if that change is the reasonably anticipated feature land use assumption and they should be integrated into the remedy selection.

00:35:00.000 --> 00:35:09.000
The agencies should refer to the 1995 line use directive and may need to supplement or revise other key documents such as the baseline risk assessment.

00:35:09.000 --> 00:35:21.000
The real investigation feasibility study or our IFS or the proposed plan.

00:35:21.000 --> 00:35:26.000
Next we have a pull. Gee, would you please queue up the poll?

00:35:26.000 --> 00:35:32.000
Absolutely. All right, Ladies, I'm gonna click a few buttons here and we are gonna pull up that poll.

00:35:32.000 --> 00:35:38.000
And we'll launch the poll here as I'm calling up on the screen.

00:35:38.000 --> 00:35:48.000
Okay, so we have this scenario where we'll ask you to apply your understanding. You can't see the narrative on the slide, you can move the poll window or slide it out of the way, but I'll also read it to you now.

00:35:48.000 --> 00:36:02.000
Laboratory X is located on a military base and is currently under federal ownership. The area is part of an NPL Superfund site and is primarily used for laboratories, office space, and parking lots.

00:36:02.000 --> 00:36:13.000
The military base plans to transfer ownership of the lab and its associated buildings to city ownership in the future. So the question we're asking you to consider, what is the anticipated future land use for this site?

00:36:13.000 --> 00:36:23.000
You'll see a series of options below that question and you can either select A residential. Be agricultural, see industrial or D recreational.

00:36:23.000 --> 00:36:33.000
So consider that information and then simply click the circle to the left of the answer and submit your response. It looks like about 40, almost 50% of you have submitted an answer.

00:36:33.000 --> 00:36:43.000
We will talk about the response and what the correct answer is in this situation in just a moment. So I'll give you all a few more seconds to consider your answer and to submit your vote.

00:36:43.000 --> 00:36:52.000
Remember if you're having any problems with that poll, we the slides are there on the screen and you can simply type your response into a message in the QA if that's easier.

00:36:52.000 --> 00:36:57.000
So it looks like about 2 thirds of the audience have cast their results and I see those responses slowing down.

00:36:57.000 --> 00:37:01.000
So I'll go ahead and end the poll here in 3, 2. One and let's take a look at the results.

00:37:01.000 --> 00:37:12.000
About 83% of the audience picked C industrial. But some people felt it might be A residential. What's the right answer?

00:37:12.000 --> 00:37:16.000
Great. Well, great job. The right answer is industrial. The current plan use is industrial and it is intended that it will stay that way since it's a large infrastructure.

00:37:16.000 --> 00:37:30.000
Laboratories office space and parking lots. So if you selected and just tell you are correct. And if you selected, residential, that's okay too.

00:37:30.000 --> 00:37:36.000
Like, if that worked, if the land use for to change left there's, we don't know what.

00:37:36.000 --> 00:37:43.000
What the site looks like and if it's in an area that has other residential areas around it, it could change in the future.

00:37:43.000 --> 00:37:51.000
And if that were the case, then they would have to go back and look at the risk assessments and see if that is a possible reuse.

00:37:51.000 --> 00:37:58.000
Good job everybody. Hello, we will move on to the next slide. And continue talking about.

00:37:58.000 --> 00:38:08.000
That the, the 2010 reduce directive. So what happens between?

00:38:08.000 --> 00:38:14.000
So what happens if your rod is already signed and the there's a radius. This happens all the time.

00:38:14.000 --> 00:38:20.000
And that's why the 2010 reuse directive was introduced because many sites are already passed.

00:38:20.000 --> 00:38:28.000
RAM of the selection and Regents wanted to know what to do if a reasonably anticipated future use change after the rod assigned.

00:38:28.000 --> 00:38:38.000
And that is gonna address in the 1995 land use directive. So the 2010 reduce directive also considers this scenario.

00:38:38.000 --> 00:38:49.000
And when I land use change occurs after Rod is signed, the Lead Federal Agency and EPA should evaluate the proposed change to see whether it will affect the protectiveness of the remedy.

00:38:49.000 --> 00:39:04.000
And if Friday modifications would be necessary to allow the change land use. If a change in the It's necessary a rod modification such as a proposed plan, ESD or Rata, may be necessary.

00:39:04.000 --> 00:39:12.000
And use changes are also evaluated during the 5 year review process. And then there's another federal facility, webinar for that.

00:39:12.000 --> 00:39:20.000
So if you're interested, please check that out.

00:39:20.000 --> 00:39:21.000
So for more information on this guidance, Gina has already dropped it into the, into the chat.

00:39:21.000 --> 00:39:32.000
So I highly recommend, referring to that as well.

00:39:32.000 --> 00:39:36.000
So next we have another pull. Jean, will you please take us through it?

00:39:36.000 --> 00:39:42.000
Absolutely. So I'm gonna go ahead and relaunch a similar question here, but the scenario is different.

00:39:42.000 --> 00:39:54.000
So let me send that pull back out to you. And in this case, we're asking you to consider land along a river that is part of a federal facility and PL superfund site, and it's currently under federal ownership.

00:39:54.000 --> 00:40:02.000
The area was primarily used for chemical processing activities and is being cleaned up under Circle. The city is interested in developing the land for hiking trails.

00:40:02.000 --> 00:40:12.000
This situation what is the anticipated future land use for the site is it A residential B agricultural, C industrial or D recreational?

00:40:12.000 --> 00:40:16.000
Again, we'll ask you to click the circle to the left of your answer and then hit submit.

00:40:16.000 --> 00:40:26.000
Now in this case again the audience seems completely honed in on one particular answer. So I'm gonna go ahead and close this one down here in 3.

00:40:26.000 --> 00:40:36.000
2, one. And looking at these results, almost a hundred percent of the responses pick D, recreational.

00:40:36.000 --> 00:40:45.000
Oh, that's impressive. Great job. That is the correct answer. It will be recreational because the city plans develop develop it for hecky trails.

00:40:45.000 --> 00:40:53.000
It's a great job.

00:40:53.000 --> 00:40:54.000
All right, now we're going to go back to the, the 2010 Ruse directive.

00:40:54.000 --> 00:41:07.000
In summary, productive reuse of a site can provide many benefits to community and support the effectiveness of remedy selection.

00:41:07.000 --> 00:41:17.000
For example, reusing a site can avoid inappropriate activities such as illegal dumping or off road vehicle use and extend the remedies protectiveness.

00:41:17.000 --> 00:41:26.000
Widespread support of the properties reuse activities. They also result in increased interest in maintaining the effectiveness of the remedy.

00:41:26.000 --> 00:41:47.000
These can also benefit communities by maintaining or increasing property values for land on and near a site as well as improving quality of life through a amenities such as a parks, open spaces and providing significant local economic benefits and neighborhood identity.

00:41:47.000 --> 00:41:51.000
Oh, I didn't realize that did that.

00:41:51.000 --> 00:41:57.000
Next, we'll talk about institutional controls.

00:41:57.000 --> 00:42:11.000
EK defines institutional controls as non-engineered instruments such as in it. Administrative and legal controls that help to minimize the potential for exposure to contaminate it.

00:42:11.000 --> 00:42:26.000
And termination or and or protect the integrity of a response action. I say typically are designed to work by limiting land use and or resource use or by providing information that helps modify or guide human behavior at a site.

00:42:26.000 --> 00:42:36.000
Institutional controls are a subset of land use controls for looks. Lucks include engineering and physical barriers such as fences and security guards, as well as ICs.

00:42:36.000 --> 00:42:57.000
The federal facility program may use either term ICs or relax interchangeably. I want to point out that ICCs are part of the selective remedy and are required at any federal facility site that leaves waste in place or has not achieved QUEUE, UE, UE, UE, UE, and, Restricted, Exposure.

00:42:57.000 --> 00:43:00.000
As an example, a selected remedy that includes a response action of a capped plan fill relies on an IC to help ensure protectiveness.

00:43:00.000 --> 00:43:13.000
And I see your luck is necessary to prohibit heavy machinery usage on a on or near a cap site.

00:43:13.000 --> 00:43:20.000
Well, allowing for light recreational land uses such as a soccer field that do not result in unacceptable risk.

00:43:20.000 --> 00:43:30.000
As components of reveal actions, essential controls are used to achieve the precise restrictions articulated in the decision documents.

00:43:30.000 --> 00:43:35.000
That are needed to at a site to achieve cleanup objectives.

00:43:35.000 --> 00:43:50.000
Also, I've recommend. Looking at the institutional control guidance that will we also call it the prime guidance that will be inserted to this chat.

00:43:50.000 --> 00:43:54.000
Alright, now I'm gonna turn it back over to Emmy.

00:43:54.000 --> 00:43:58.000
Thank you, Jill. Thank you so much for taking us through reuse. We're going to talk about.

00:43:58.000 --> 00:44:03.000
Brack for a second starting off with an example of a success that was had at a Braxite in Myrtle Beach.

00:44:03.000 --> 00:44:16.000
So in the pictures you see here, we the Myrtle Beach Air Force Base, I should say, Farmer was a 3,900.

00:44:16.000 --> 00:44:27.000
Oh, apologies. 3,900 acre site. But now it hosts Myrtle Beach International Airport, over 1,200 new homes.

00:44:27.000 --> 00:44:39.000
Lots of parks walking past sporting facilities to you know really engage the community a golf course a college there's a business park there as well and a booming commercial district.

00:44:39.000 --> 00:44:48.000
The So for those who are less familiar with brackets, talk a little bit more about. What base closures are.

00:44:48.000 --> 00:44:51.000
So for closures at bases where cleanup is being conducted, you can have a few different scenarios.

00:44:51.000 --> 00:45:03.000
I should also mention that, you can have a few different scenarios. I should also mention that EPA, EPA was more heavily involved in cleanup at Brack site up until about 2016.

00:45:03.000 --> 00:45:04.000
I believe that was the fifth round of brack. And after that time, EPA has not been as involved.

00:45:04.000 --> 00:45:18.000
We essentially. Those resources were pulled for EPs participation in 2016. But we still have some great and the cleanup is still happening.

00:45:18.000 --> 00:45:27.000
There's some great reuse successes that are happening and we love to recognize those. With base closures, you could have a couple of different scenarios.

00:45:27.000 --> 00:45:36.000
It might be that a base is going to be closed but the plan is for that land to remain in the Department of Defense ownership with no plans for transfer.

00:45:36.000 --> 00:45:48.000
You could have a scenario where base closure is happening, but there are established plans to transfer the land that considers zoning anticipated reuse all of that.

00:45:48.000 --> 00:45:55.000
And there's also base closures where the plan is to transfer the land back to another federal agency.

00:45:55.000 --> 00:46:17.000
So that property transfer has a specific process that it has to go under. So when you're looking at cleanup of a different petrol facility site, the land use assumptions at sites undergoing base closure may be different than at sites where the federal agency is planning to maintain control of the facility.

00:46:17.000 --> 00:46:25.000
Essentially in perpetuity with no plans to transfer it up to any party or any other federal agency.

00:46:25.000 --> 00:46:32.000
So yeah, we just wanted to touch on that. Lots of successes there, although EPA does not play a big role as of 2,016.

00:46:32.000 --> 00:46:39.000
These clean ups are ongoing and they are part of considerations for the reuse awards right Joe we can consider.

00:46:39.000 --> 00:46:48.000
The sites and clean ups.

00:46:48.000 --> 00:46:59.000
Awesome. Alright. So we okay just wanted to touch on brack before we continued on at this time though I would like to hand over the mic to our other instructor, Jeff.

00:46:59.000 --> 00:47:05.000
I'll give him an opportunity to introduce himself and he'll talk to us about onsite and offsite determinations.

00:47:05.000 --> 00:47:16.000
Well, good day, everyone. Yeah, thank you, Emmy. We're gonna talk a little bit about on site and off-site determination, so we'll get right into it.

00:47:16.000 --> 00:47:21.000
Before we get going, let's start with a group poll. So what I want to ask is what challenges have you dealt with in onsite and off-site determinations?

00:47:21.000 --> 00:47:22.000
So Jill, will you guide us through that, please? Or excuse me, Gene.

00:47:22.000 --> 00:47:29.000
Yes, that is a category of our.

00:47:29.000 --> 00:47:37.000
That's okay. So this is a pretty straightforward question and the response is going to come in a form by sending a message in the Q&A.

00:47:37.000 --> 00:47:42.000
So there's no new floating window. I'll simply direct those of you to who haven't done so yet.

00:47:42.000 --> 00:47:50.000
Go ahead and click the QA box on your screen and let's go ahead and type in your response to that question by sending a message into the Q&A.

00:47:50.000 --> 00:47:59.000
What challenges have you dealt with in onsite offsite determinations? And then I'll start summarizing some of those responses as they come in.

00:47:59.000 --> 00:48:05.000
If you've had no challenges, you can put no challenges in as a response. We will take that.

00:48:05.000 --> 00:48:11.000
Just in the interest of time, we don't have the opportunity to take any verbal comments here, but I am seeing some responses.

00:48:11.000 --> 00:48:16.000
So many, I've got a number of people who are saying they've had no challenges. Because they're new employees.

00:48:16.000 --> 00:48:22.000
So they haven't yet had the opportunity to experience this. Others are chiming in that they've had local tribal considerations.

00:48:22.000 --> 00:48:31.000
There's been a challenge defining on-site treated wastewater final destinations. Institutional controls.

00:48:31.000 --> 00:48:37.000
And, someone was kind enough to just say many in all capitals. They've just had many challenges.

00:48:37.000 --> 00:48:45.000
Unrealistic expectations of the local community. There were limitations. They had UXO in off base areas and offshore.

00:48:45.000 --> 00:48:55.000
A few other people again chiming in with Tribal. There was a third party who performed work under an IC and they weren't sure if the offset rule would apply or not.

00:48:55.000 --> 00:48:56.000
But it looks like without a doubt most people are new and they have not yet had a chance to have a challenge.

00:48:56.000 --> 00:49:03.000
That's the most common answer I'm seeing.

00:49:03.000 --> 00:49:04.000
Hi.

00:49:04.000 --> 00:49:11.000
Well, very good. Thank you for taking the time to answer. I will, we're gonna have a couple of examples.

00:49:11.000 --> 00:49:22.000
Of the site that I'm a project manager on, which is the hand for nuclear reservation. And I've been with the agency for just about 3 years, so I know exactly what it feels like to be new so you're not alone.

00:49:22.000 --> 00:49:24.000
But we'll talk about the Hanford site and a couple of other examples of, determinations, as we go through.

00:49:24.000 --> 00:49:38.000
So thank you for your input and hopefully by the end of this you'll have a little more understanding of how to go through this process if you have not before.

00:49:38.000 --> 00:49:41.000
So we'll get it started.

00:49:41.000 --> 00:49:55.000
So off-site determinations. What is the off-site rule? Well, it applies to any circular response action involving the off-site transfer of any hazardous waste substance pollutant or contaminant, also known as circle waste.

00:49:55.000 --> 00:50:00.000
Circle of waste may may only be placed in a facility operating in compliance with the resource conservation and recovery act or RICRIP or other applicable federal or state.

00:50:00.000 --> 00:50:18.000
Requirements. What is the purpose of the OCR? The purpose of the OCR is to ensure circular does not contribute to present or future environmental problems.

00:50:18.000 --> 00:50:19.000
So the interpretation of the OSR originates from the the NCP, the national contingency plan.

00:50:19.000 --> 00:50:28.000
At 400 CFR, 300.4 40 titled procedures and planning and procedures for planning and implementing off site response actions.

00:50:28.000 --> 00:50:48.000
The OCR establishes the criteria and procedures for determining whether facilities are acceptable for receipt of circle waste from response actions authorized or funded under circa and that's that's one that I think is important because oftentimes we think about a response action being done by a federal agency.

00:50:48.000 --> 00:51:12.000
EPA or a private party but also applies to any action that's funded by super fund or It also establishes compliance criteria and release criteria and establishes a process for determining whether facilities are acceptable based on those criteria.

00:51:12.000 --> 00:51:33.000
For the purpose of the OSR. As I discussed is to avoid having circle of waste from response actions authorized or funded under Circle to contribute the present or future environmental problems by directing these waste to management units determined to be environmentally sound.

00:51:33.000 --> 00:51:59.000
So though that is the exact verbiage for understanding that rule. And in your on the homepage that Jill talked about and in your participant manual you'll see some links and one of them is for the fact sheet for the off-site rule so you can check that out if you're curious about.

00:51:59.000 --> 00:52:21.000
So off-site determinations, what actions are affected? Well, any. Remedial or removal action involving the off-site transfer of any hazardous substance, pollutant or contaminant that is conducted by EPA, state, private parties, or other federal agencies and or if the action is super fund financed.

00:52:21.000 --> 00:52:32.000
Included are clean ups at federal facilities under section. 100, and 20 of circa and cleanups under section 3 11 of the Clean Water Act or CWN.

00:52:32.000 --> 00:52:41.000
Except for cleanup of certain petroleum. Materials that are exempt with circa. If no circle of funds or authorities are involved or the waste is not circle of waste.

00:52:41.000 --> 00:52:50.000
The OSR does not apply.

00:52:50.000 --> 00:53:09.000
So this here is a picture of what is called the, well, together it's called the liquid waste processing facilities, but at the lower part of your screen, have affluent treatment facility and above it is, excuse me, the, yeah, above it is the liquid affluent retention facility on the Hanford site.

00:53:09.000 --> 00:53:23.000
So the affluent treatment facility or ETF and the liquid affluent retention facility make up the entire liquid waste processing facility used to store, treat, and dispose of large volumes of waste on the Hanford site.

00:53:23.000 --> 00:53:40.000
It is a Washington state permitted facility under the site the Hanford site wide ricper permit and Washington state over in our state, Washington state has an authorized RICK WRI program.

00:53:40.000 --> 00:53:48.000
So it's geographically located in what we call the 200 area NPL site, but is considered off site for remedial action.

00:53:48.000 --> 00:53:56.000
So it sits within the site, but it is permitted and considered off site for remedial actions.

00:53:56.000 --> 00:54:01.000
The affluent treatment facility, ETF, we call it, receives liquids from.

00:54:01.000 --> 00:54:11.000
Liquid affluent retention facility or lurf. Which is permitted by the state and has 3 storage basins designed to hold about 23 million gallons of material.

00:54:11.000 --> 00:54:18.000
And you'll see in the picture there that it has a excavated lurf basin 41.

00:54:18.000 --> 00:54:25.000
I know that that is actually lined now. I can't remember if it's in operation, but it has expanded recently.

00:54:25.000 --> 00:54:33.000
So this is a little bit of an outdated picture, but it gives the idea of the LerF facility.

00:54:33.000 --> 00:54:42.000
Where if stores liquid waste, ETF treats them, Lerf accepts and stores waste waters from a number of sources on the Hanford site.

00:54:42.000 --> 00:54:59.000
Once wastewater has been treated through. ETF or the affluent treatment facility, it is stored until test, test confirmed that various radioactive and hazardous contaminants have been removed or lowered to levels that make it acceptable for discharge to a state approved disposal site within the Hanford.

00:54:59.000 --> 00:55:26.000
200 area, as we call it. The treated waste is then discharged as non-hazardous waste and secondary waste from these treatment processes is concentrated into it and dried into a powder in the ETF secondary treatment system or excuse me the train packaged and sent to and I'll talk a little bit about it later but it's sent to the Hanford environmental restoration and disposal

00:55:26.000 --> 00:55:35.000
facility.

00:55:35.000 --> 00:55:40.000
So for the Spring Hill landfill that we have here, I think we have a video for this.

00:55:40.000 --> 00:55:45.000
Is that right, Gene?

00:55:45.000 --> 00:55:51.000
We absolutely do. And I'm gonna call that video up right now. It's coming up here on the screen.

00:55:51.000 --> 00:56:05.000
Okay, so hello, I'm Rob Pope. I am a senior RPM in region 4 Atlanta, Georgia and I have done some of this determining land use and determining on site and off site.

00:56:05.000 --> 00:56:14.000
For different uses as we go through the, action and I'm happy that you guys can sit in on this webinar.

00:56:14.000 --> 00:56:25.000
So here is an example. Of a very common off-site rule. Facility. This is called the Spring Hill landfill.

00:56:25.000 --> 00:56:32.000
It is in northwest Florida. It receives waste from Tyndale Air Force Base regularly.

00:56:32.000 --> 00:56:49.000
It is basically a subtitle D ricper permitted landfill. And so it, it is a, a solid wasteland fill so they cannot take hazardous waste but there's a lot of the waste that comes off the base that is not hazardous waste that still is circle of waste.

00:56:49.000 --> 00:57:02.000
And so this facility has to be circle off-site rule. Approved and basically What happens is the the facility which is managed by waste management is in contact with the off-site little coordinator.

00:57:02.000 --> 00:57:09.000
Each region has one. They're normally in the Rick Red division or the division that holds the RIP group.

00:57:09.000 --> 00:57:18.000
And then that offside room coordinator can tell you if the facility you're looking at is off site rule, authorized.

00:57:18.000 --> 00:57:27.000
This one has also received waste from Deepwater Horizon, for instance. And, and so we used it under other circular response actions.

00:57:27.000 --> 00:57:38.000
It's about 68 miles from Temple Air Force Base. So it's not insignificant to truck things 68 miles from the base which is right on the edge of the water to this landfill.

00:57:38.000 --> 00:57:55.000
It's upper in the upper part of the county well above flood lines and hurricane concerns. But it's a good safe option to put that subtlety waste and sometimes what Tyndale has had to do is treat and stabilize waste so that it is not hazardous waste and then they can ship it to this landfill.

00:57:55.000 --> 00:58:08.000
It's like feels very careful about checking to make sure that they that it has been treated. One thing to be aware of with these off-site rule facilities is that the determinations do expire.

00:58:08.000 --> 00:58:18.000
The offside rule coordinator doesn't give them a carte blanche. It's it's yes right now it's fine because if they start having violations of the ripple permit of the state or something like that.

00:58:18.000 --> 00:58:31.000
The offside rule coordinators should be aware of those and will probably take away that off-site rule determination until they have a address those concerns from the state authorized permit and it doesn't have to be a richer or landfill, it can be some other kind of landfill, but it has to have this off-site rule acceptability.

00:58:31.000 --> 00:58:51.000
And this is the probably the most common one of the subtitle D landfills. I'm, I'll see landfills of course always have these as well.

00:58:51.000 --> 00:58:59.000
Thank you, Jean. So let's talk for a moment about permit requirements. So permit requirements.

00:58:59.000 --> 00:59:12.000
Permits are required for circular work conducted off-site but not on site. The NCP, section, 40 CFR 300 dot 40 states that.

00:59:12.000 --> 00:59:32.000
No federal, state or local permits are required for onsite response actions. Conducted pursuant to circle sections 10410612121 or 1 22 The term on site means the aerial extent of contamination and all suitable areas.

00:59:32.000 --> 00:59:48.000
In very close proximity to the contamination necessary for implementation. Of the response action. So again, permits are, permits if required shall be obtained for all responsive activities conducted off-site.

00:59:48.000 --> 00:59:56.000
And notice note that the site is defined in the record of decision. So in the rod is done, the site is defined in the rod.

00:59:56.000 --> 01:00:12.000
While while party while responsible parties or federal facilities are not required to obtain a permit for on-site activities they must meet the substantive requirements of the various statutes that do apply.

01:00:12.000 --> 01:00:13.000
So I'm, oh yeah, go ahead.

01:00:13.000 --> 01:00:22.000
Jeff, actually, I'm gonna, I'm gonna jump in here. I'm so sorry, just to interject.

01:00:22.000 --> 01:00:23.000
Oh, very good.

01:00:23.000 --> 01:00:31.000
We have been going pre to you far and we did not pause yet for questions so I apologize we are doing great on time and I want to stop before we go any further and make sure we take just a few moments here for a few questions if that's okay.

01:00:31.000 --> 01:00:32.000
Yeah.

01:00:32.000 --> 01:00:38.000
So I'm going to go ahead and add the other speakers in on the queue. With our video sources so that we can start to take some of those questions as they're coming in.

01:00:38.000 --> 01:00:46.000
If you've already typed in a question into the QA window, don't worry. It's in there if you are in the middle of typing it in, keep typing it in.

01:00:46.000 --> 01:00:56.000
We're gonna start with a few questions that came in earlier. And, I mean, I'm gonna direct the question to you and hopefully you can help, move it through the presenters as needed.

01:00:56.000 --> 01:01:03.000
So if it's okay, there were a few questions that came in. Earlier about changing, land use scenarios.

01:01:03.000 --> 01:01:10.000
And so one of the attendees noted that they understood how a federal facility can change their use in the future.

01:01:10.000 --> 01:01:21.000
So for example, going from a residential scenario to a commercial or industrial use because they're going from a more conservative risk situation to a less conservative situation.

01:01:21.000 --> 01:01:30.000
But if it was the opposite, so let's say it was a commercial or industrial land and then they wanted to change it to a residential use.

01:01:30.000 --> 01:01:44.000
And the cleanup goals were met for those industrial receptors. Would the government come out to that federal facility and then reassess or perform additional cleanup if it's going to shift over to residential use.

01:01:44.000 --> 01:01:52.000
So, would the government come out and check? I would say it's the responsibility of the lead agency to ensure that the remedies remain protective.

01:01:52.000 --> 01:02:02.000
That's also part of the reason why we do five-year reviews at sites that leave waste in place that don't allow for unlimited use unlimited exposure.

01:02:02.000 --> 01:02:09.000
So yes, the lead agency along with the regulatory agencies are going to look at that change in land use.

01:02:09.000 --> 01:02:19.000
And that this is not a hypothetical, this has happened at several federal facility sites where perhaps when the cleanup was done, they thought it was going to remain industrial.

01:02:19.000 --> 01:02:20.000
15 years later, population is growing and now there's interest in putting condos or what have you.

01:02:20.000 --> 01:02:40.000
Residential. Housing on that land. So before that can happen, we had mentioned earlier those pathways have to be reevaluated to see if the cleanup that was implemented is protective enough to support that new land use.

01:02:40.000 --> 01:02:48.000
If not, there may be necessity for ESD or a rod amendment to be issued to conduct additional activities to meet that protectiveness.

01:02:48.000 --> 01:02:54.000
Jill, did you want to add anything? Did I miss anything on that?

01:02:54.000 --> 01:03:05.000
No, I think that was a perfect explanation. Definitely that we do see that a lot and we support if it's a more conservative land reuse and oftentimes sort of, so does other federal agency.

01:03:05.000 --> 01:03:18.000
So we go through the risk assessments and all the documents that we described before to make sure that the if we have to make modifications to the remedy that we will do that and that the site will be protective.

01:03:18.000 --> 01:03:27.000
Right, excellent. We did have a quick question on one of the early poll questions asking about laboratory X in that scenario.

01:03:27.000 --> 01:03:34.000
They were just curious, how would you know that the land use changed from industrial to residential? Is there notification process that happens?

01:03:34.000 --> 01:03:51.000
Yes. Yes, definitely. If there is a line use control, EPA, it has to be consulted a part of the enforcement documentation with institutional controls, which are necessary for any federal facilities to refund site that has waste left in place.

01:03:51.000 --> 01:04:06.000
Has enforceable information in that document that states that the, of the EPA and the states, if they're part of the FFA need to be notified and have concurrence with that change that land use change.

01:04:06.000 --> 01:04:12.000
So the other federal agencies or property owner cannot just change. So the other federal agencies or property owner cannot just change the line use control without coordinating with EPA.

01:04:12.000 --> 01:04:25.000
Okay. And then talking about those categories for anticipated future use. One of the attendees wanted to know why is commercial, not a category that's used in your anticipated future use scenarios.

01:04:25.000 --> 01:04:39.000
Is commercial equivalent in or included with the phrase industrial. They note that a lot of municipalities use the term commercial in their zoning regulations and potentially exposed populations are different than those in an industrial setting.

01:04:39.000 --> 01:04:43.000
So they're wondering if you could talk about that category.

01:04:43.000 --> 01:04:54.000
Sure, I'll take that question. Our EPA, our, we have this, guys called, and I'm gonna, it's one of those acronyms that we use that I can't recall what it stands for right now.

01:04:54.000 --> 01:04:55.000
It's one of those acronyms that we use that I can't recall what it stands for right now.

01:04:55.000 --> 01:04:56.000
Okay.

01:04:56.000 --> 01:05:07.000
Maybe we can help me, but that's our risk assessment guidance. And, it has those 4 categories that any discuss, air cultural, industrial, residential and recreational.

01:05:07.000 --> 01:05:14.000
And so that's what we don't deviate from those 4 categories, even though commercial probably is part of the industrial use category.

01:05:14.000 --> 01:05:24.000
Our regs are set up to, look, at, have, risk, scenarios, for, each, of, those, for,

01:05:24.000 --> 01:05:35.000
Okay, we just have a question here in terms of what's the most conservative, reuse would is residential, considered to be the most conservative reuse scenario.

01:05:35.000 --> 01:05:36.000
Yes.

01:05:36.000 --> 01:05:54.000
Okay, alright, excellent. How about if your LUCKs, your LUCs, are required for federal facilities that don't meet you, UUE, and we have acronyms coming in and I know there's some new people, so instructors, please feel free to define the acronyms in your response.

01:05:54.000 --> 01:05:55.000
Okay.

01:05:55.000 --> 01:06:00.000
Then they ask who is responsible for restricting and verifying the Lux are in place and effective?

01:06:00.000 --> 01:06:06.000
Does this tie into 5 year reviews? And then who would be the anticipated lead reviewer for compliance?

01:06:06.000 --> 01:06:09.000
Is it Fed, states, local, tribal?

01:06:09.000 --> 01:06:25.000
Sure. I'll take that question as well. That's a good question. You, you, says for unrestricted use and restricted exposure and it's land use controls or institutional controls are required at any site that federal facility superfront site that does not achieve, U, UE.

01:06:25.000 --> 01:06:35.000
There's a part of the record. Record of decision and decision documents for the site will have all the language for that use controls.

01:06:35.000 --> 01:06:47.000
I object to that we have a language control checklist on our website that I will provide the link to in a moment but if you have all that language in there decision documents that will be enforceable.

01:06:47.000 --> 01:06:57.000
They are, if with that language the Usually it's the other federal agency, but if they transfer the property, they'll.

01:06:57.000 --> 01:07:12.000
They'll transfer the responsibility to the transfer. But there is their responsibility to annual respect inspections on the property to make sure that the land use controls are effective and that that land uses states of savings has not changed.

01:07:12.000 --> 01:07:20.000
And, and then furthermore, anytime there is a federal facility with waste left in place, a 5 year review is required.

01:07:20.000 --> 01:07:29.000
And so we'll do that and that's another way to make sure that the learning is Glad use is maintained and doesn't change.

01:07:29.000 --> 01:07:31.000
I think I answered all that question. It was a long question, so please let me know if I, like this anything.

01:07:31.000 --> 01:07:36.000
Okay. Alright, excellent. Thank you. Let's, take another question here.

01:07:36.000 --> 01:08:03.000
Why would you not want an LUC or a Lock restricting residential use? If your risk assessment or remedy is based on future commercial industrial reuse, they just note that by including a residential restriction in your decision document, one could figure out pretty quickly if it was the failure to evaluate current potential residential use in the RI or and or your HH RA.

01:08:03.000 --> 01:08:14.000
So your human health risk assessment. There are instances that they note where necessary data was collected in the RI but not evaluated in the human health risk assessment because of reasonably anticipated reuse.

01:08:14.000 --> 01:08:22.000
And then other instances were the necessary data. We're never collected. So they just wanted to know if you could provide clarification on that.

01:08:22.000 --> 01:08:31.000
Why would you not want a lock restricting residential use if the risk assessment is based on future commercial industrial reuse.

01:08:31.000 --> 01:08:47.000
Well, first I'll answer that question. Anytime that you, UE, UE, UE, UE, or, LUCK is required because we want to make sure that 20 years down the road when we want to make sure that 20 years down the road when we all retire that someone doesn't come along and be like, oh, this would be

01:08:47.000 --> 01:08:48.000
a great place to put a condo and be like, oh, this would be a great place to put a condo and it has a lot of contamination.

01:08:48.000 --> 01:09:10.000
So we just wanna make sure that documentation is in place. In terms of the risk assessment, I'm not sure if I understood the question, but like we see it both ways where sometimes like the example that any game with NASA that they'll include residential to have a conservative risk assessment and we like to see that because line uses can change and it's good to have that documentation already.

01:09:10.000 --> 01:09:22.000
So if there is a change, we can, see, like, what, the, risk, are, and, what, the, changes, to, the, middle, Yeah.

01:09:22.000 --> 01:09:23.000
So that's site specific.

01:09:23.000 --> 01:09:31.000
Okay. Okay. Okay. Alright, and we did have, I would say a seasoned staff member who just shared, an experience.

01:09:31.000 --> 01:09:40.000
They shared a comment that some of the federal facility rods are so old. That trying to figure out what additional work needs to occur in order to change future land use can be a very, complex and paraphrasing.

01:09:40.000 --> 01:09:50.000
And just a cautionary note that there's sometimes a lot of effort that needs to go in, to the work to decide what needs to go in, to the work to decide what needs to go in to the work to decide what needs to happen to change the future.

01:09:50.000 --> 01:09:57.000
And, what needs to happen to change the future land use. I'm seeing nodding heads.

01:09:57.000 --> 01:09:58.000
Yeah.

01:09:58.000 --> 01:10:04.000
So it sounds like the instructors understand that comment and that perspective. Okay, excellent. A quick question here on offsite determinations.

01:10:04.000 --> 01:10:05.000
Yeah.

01:10:05.000 --> 01:10:06.000
When when you're looking at offset determinations at a circus site, what do you consider air discharges?

01:10:06.000 --> 01:10:20.000
Or treated affluent? Liz, is it surface water? Like if that's going quote off site and would therefore require a permit.

01:10:20.000 --> 01:10:21.000
Okay.

01:10:21.000 --> 01:10:26.000
I would say we're gonna cover this in Jeff's next section very much in detail so we can table that question and see if it gets gets answered.

01:10:26.000 --> 01:10:27.000
Thank you.

01:10:27.000 --> 01:10:30.000
Alright, well then I think in the interest of time, let's progress and go back to the presentation.

01:10:30.000 --> 01:10:31.000
There's something.

01:10:31.000 --> 01:10:36.000
Thank you all so much for letting me interject and we'll carry on.

01:10:36.000 --> 01:10:40.000
Very good. And thanks for waiting on that question. And I hope that we're able to touch on that.

01:10:40.000 --> 01:10:47.000
And if not, we can we can circle back and and talk more about that. Right now I'm going to read a scenario regarding former Weldon Springs ordinance works in Missouri.

01:10:47.000 --> 01:11:08.000
This was a chemical plant and you could see the picture here, an older picture of the chemical plan and then a picture of an observation, an older picture of the chemical plan and then a picture of an observation platform after it was cleaned up a 75 foot tall permanent disposal cell that was created through the cleanup process.

01:11:08.000 --> 01:11:15.000
So the Weldon Spring, former Army Ordnance Work Site or WSW is in St.

01:11:15.000 --> 01:11:18.000
Charles County, Missouri, approximately 30 miles west of St. Louis. The site encompasses a approximately 17,232 acres.

01:11:18.000 --> 01:11:38.000
Including mixed areas of ownership, state and federally owned land parcels. The Army acquired the property in 1940 and began production of try nitro toluene or TNT.

01:11:38.000 --> 01:11:47.000
And dinitro, or excuse me, dinitro tell you in D and T in 1,941 to support the World War II efforts.

01:11:47.000 --> 01:12:01.000
The Army constructed 18 identical TNT and 2D and T manufacturing plants beginning in May, the nineteenth 41 in the area now known as Weldon Springs training area or WSTA.

01:12:01.000 --> 01:12:11.000
Following the activation of the part of the production facility in 1,945, the majority of the property was transferred to the state of Missouri and local entities.

01:12:11.000 --> 01:12:19.000
Historical Army operations resulted in the release of hazardous substances to the soil and groundwater at the site.

01:12:19.000 --> 01:12:23.000
The site was listed on the national priority list in February of, 1,990 and a federal facility agreement.

01:12:23.000 --> 01:12:35.000
You've heard us talk about them for some of your new folks. That's FFA, became effective on August eighth in 1,991.

01:12:35.000 --> 01:12:41.000
The WSW site surrounds and is a adjacent to the Weldon Springs Quarry Plant and Pits site.

01:12:41.000 --> 01:12:54.000
The Weldon Springs Cory plant and pit site is a separate NPL site listed in 1,989 the department of energy is the lead agency for the, Cory Pit plant site.

01:12:54.000 --> 01:13:03.000
So you could have the army, you have the state, you have the Department of Energy, so it can you can see it can get a pretty pretty complicated sometimes.

01:13:03.000 --> 01:13:18.000
Pardon me. So on August 9, 1994, Missouri invoked the Ffa's dispute resolution procedures regarding the state's authority to require permits for the incinerator.

01:13:18.000 --> 01:13:27.000
Contaminated wastewater treatment, and storm water runoff activities that are described in the draft final record of decision.

01:13:27.000 --> 01:13:38.000
On September seventh in 94 the dispute resolution committee elevated the matter to the senior executive. Unable to unanimously resolve the dispute.

01:13:38.000 --> 01:13:46.000
It was elevated to the regional administrator. Of within the EPA. As provided in the dispute resolution procedures of the federal facility agreement, Missouri elected to elevate the region's decision for resolution.

01:13:46.000 --> 01:14:07.000
And I just want to interject that this is elevated to the administrator of the EPA. So these decisions within NPL sites are decided by the administrator of the EPA.

01:14:07.000 --> 01:14:13.000
In this case, it is, undisputed that the response actions at issue will be conducted, constructed entirely within the geographical area.

01:14:13.000 --> 01:14:39.000
Considered the NPL site. Missouri's position is that because of site, site, excuse me, off site releases and discharge will occur, the state may seek to require the Army to obtain permits throughout this dispute the Army has asserted that permits are not required for subject activities.

01:14:39.000 --> 01:14:52.000
Furthermore, the Army has stated that it is unwilling to jeopardize the ability to carry out its circular responsibilities by agreeing to apply for a state permit that Circle it does not require.

01:14:52.000 --> 01:15:17.000
Missouri contends that that what constitutes on site in EPA's view is overbroad and that the response actions under the selected remedy will inevitably result result in extended off-site discharges beyond the quote unquote on site area and thus require state permits.

01:15:17.000 --> 01:15:47.000
So EPA has long viewed response actions that may have discharges or release or releases with subsequently migrate via with subs, which subsequently migrate beyond site boundaries as qualifying for circular 121, E one, EPA excerpts that circle section 1 21 and the corresponding provision of the NCP at 300.400 EI as Exempting response actions conducted entirely on

01:15:51.000 --> 01:16:02.000
site even if the actions involve discharges or emissions that result in subsequent migration of contaminants beyond the site boundaries.

01:16:02.000 --> 01:16:14.000
Since some off-site migration is likely to occur, the the virtual in virtually all cases where there is an on-site discharge or emission, adopting the state's interpretation would greatly narrow the kinds of permits which the exception applies.

01:16:14.000 --> 01:16:44.000
So in this case, the EPA administrator, at the time, Carol Brownner's decision stated that the EPA interprets and the corresponding provisions in the NCP as exempting response actions conducted entirely on site, even if the actions involve discharges or emissions that result in sub subsequent migration of contaminants beyond the site boundary.

01:16:49.000 --> 01:16:57.000
So as previously mentioned while responsible parties and this is regarding onsite determination.

01:16:57.000 --> 01:17:09.000
As previously mentioned, while responsible parties or federal facilities are not required to obtain a permit, they must meet requirements and the permits and and various statutes that apply.

01:17:09.000 --> 01:17:23.000
So even though the permit is not required, the requirements within the statutes do apply. The resource conservation recovery act is a good example of this and must be adhered to and handling hazardous wastes on site.

01:17:23.000 --> 01:17:35.000
For example, small quantity generators can only keep their waste on site for 180 days or 270 days if they're treatment storage and disposal facility is more than 270 miles away.

01:17:35.000 --> 01:17:49.000
Large quantity generators or waste can be or of waste can all be store. Can only store waste for 90 days without obtaining a permit as a storage facility.

01:17:49.000 --> 01:17:57.000
Also rec, corrective active management units or camu's are used to deal with onsite hazardous waste.

01:17:57.000 --> 01:18:08.000
They facilitate treatment and, and storage and disposal, the hazardous waste managed for implementing cleanup and remove disincentives for cleanup that record can impose on these on these wastes.

01:18:08.000 --> 01:18:27.000
So these there are links and details regarding small quantity generators, large quantity generators and camus in the presentation manual that was provided as well as the homepage that Gene talked about at the beginning of the the, our presentation.

01:18:27.000 --> 01:18:32.000
So earlier I talked about the Hanford Environmental Restoration and Disposal Facility.

01:18:32.000 --> 01:18:46.000
When when I was talking about the LerF ETF. Facility. The the Hanford Environmental Restoration Disposal Facility or what we call, is in the 200 area of the Hanford site.

01:18:46.000 --> 01:18:58.000
And there's a massive. Landfill regulated by EPA under Circle out. It's established under a record of decision and was built in 1996.

01:18:58.000 --> 01:19:07.000
Erneth accepts low-level radioactive hazardous and mixed wastes that are generated during the circular cleanup remediation activities at Hanford.

01:19:07.000 --> 01:19:18.000
And it's worth noting that this disposal site only takes waste generated on site. It does not take waste generated off the Hanford site.

01:19:18.000 --> 01:19:28.000
In Hanford's, the Hanford rod states that the, that, is on site for the responses of, remedial action.

01:19:28.000 --> 01:19:35.000
Earth meets the substantive and then this is important. Earth meets the substantive requirements of ricra, but is not.

01:19:35.000 --> 01:19:47.000
A ricwer permitted landfill. So it is considered on site. The facility is designed to keep the environment safe by isolating waste and leachate.

01:19:47.000 --> 01:19:58.000
From the environment, lee sheets collected and sent to a large water treatment facility in the 200 west area where contaminants are removed.

01:19:58.000 --> 01:20:05.000
And you can see a little map here kind of where Earth is and and just just north of that is where the.

01:20:05.000 --> 01:20:15.000
Trip the the pump treat from the FREEMAN facility is.

01:20:15.000 --> 01:20:28.000
So, Earth is a large engineered landfill used for the disposal of low level radioactive chemical and mixed waste generated from demolition, remediation, and other cleanup to activities across the the Hanford site.

01:20:28.000 --> 01:20:43.000
It covers an area of approximately a hundred 7 acres and is and its size provides tremendous flexibility in disposing of different waste forms ranging from soils to large pieces of contaminated equipment.

01:20:43.000 --> 01:20:52.000
Earth is composed of 8 original disposal cells and you can see it up in the in the picture on the upper left-hand corner and 2 super cells.

01:20:52.000 --> 01:20:58.000
That are twice as large as the original cells. Each super cell is designed to hold approximately 3.6 million tons of material and the original cells were.

01:20:58.000 --> 01:21:10.000
Constructed in pairs with each cell measuring approximately 500 feet wide. 500 feet long and 70 feet deep.

01:21:10.000 --> 01:21:12.000
And you see in the in the picture there on the upper left of a black bordered proposed supersonal 11.

01:21:12.000 --> 01:21:22.000
Super cell 11 is currently in the planning phase and as the picture shows will mirror the adjacent cell.

01:21:22.000 --> 01:21:31.000
And so that is we're going through the process of planning now for Super Cell 11.

01:21:31.000 --> 01:21:41.000
So on-site terminations. On site is defined in 40 CFR 300.40 E as again the aerial extent of contamination and all suitable areas in a very close proximity to the contamination.

01:21:41.000 --> 01:21:52.000
Necessary for implementation of the response action.

01:21:52.000 --> 01:22:06.000
Used to determine that waste from a specific site or OH. You operable unit can be moved across an area outside of the OU boundary to another location technically within the larger site.

01:22:06.000 --> 01:22:19.000
So again, the definition for on site per the CFR was designed to create additional space for treatment systems that require considerable area for construction and staging areas, areas not covered by this definition are said to be off site.

01:22:19.000 --> 01:22:37.000
For example, contaminated debris, the soil may be sent to a waste disposal facility or treatment facility located at another area of the site within the boundary identified within the rod.

01:22:37.000 --> 01:22:44.000
So here is another apply your understanding and I'll read this narrow really quickly before we have the window that pulls up over it in this scenario.

01:22:44.000 --> 01:23:06.000
Would the lay down area be considered on site for the purposes of an OU one response action and you can see OU one in blue to the left and equipment lay lay down area in purple on the right and within the red NPL site.

01:23:06.000 --> 01:23:17.000
So, Here in the in the O. Hear the OU and the equipment lay down area are in close proximity one another and both are located on the same NPL site.

01:23:17.000 --> 01:23:23.000
So what do you think? Gene, you wanna queue this up and see what people are thinking?

01:23:23.000 --> 01:23:33.000
Absolutely. So there is a new pop-up poll that is on the screen asking should the lay down area be considered on site for the purposes of an OU one response action.

01:23:33.000 --> 01:23:40.000
And you're gonna have 3 answers. You can pick A, yes, B, no, or C sometimes.

01:23:40.000 --> 01:23:47.000
And then once you pick your option by clicking the circle to the left of the answer that you think is correct hit that submit button and it does look like the answers are coming in rapidly.

01:23:47.000 --> 01:23:57.000
Almost half of the audience have cast their vote. And I am looking here and double checking to see if you're unsure, that's okay.

01:23:57.000 --> 01:24:03.000
Just take your best guest and submit. Otherwise you can type a response into the QA if that's easier regarding this question.

01:24:03.000 --> 01:24:09.000
Looks like the answers are starting to slow down. So I'll go ahead and close this poll in 3.

01:24:09.000 --> 01:24:19.000
2 one And let's look. So it looks like in this case it was. About half of the audience picked A.

01:24:19.000 --> 01:24:24.000
But there was a pretty, I'm seeing some nodding heads, but the other half was split between B and C.

01:24:24.000 --> 01:24:27.000
So what's the right answer, Jeff?

01:24:27.000 --> 01:24:41.000
So this is one of those very unsatisfying answers, right, that sub times applies. So things that you want to consider in this scenario have a similar response action, have similar response actions on the site.

01:24:41.000 --> 01:24:44.000
Used a laydown area in this manner that we're located away from the OU. Is there a concern?

01:24:44.000 --> 01:24:59.000
Contamination could spread to other parts of the NPL site due to traveling between the laydown area and the OU, or what are the reasons for having the laydown area be at that location?

01:24:59.000 --> 01:25:06.000
Does it improve efficiency? So it just outlines the fact that in a case like this, sometimes it can be appropriate.

01:25:06.000 --> 01:25:22.000
Sometimes it may not. It requires discussion with all of the parties involved to figure out what is best protects you know the human health of the environment meets regulation and is appropriate for the cleanup that we're doing.

01:25:22.000 --> 01:25:28.000
I know it's very unsatisfying, but you know it's we do have to have some of those questions.

01:25:28.000 --> 01:25:33.000
So anyway. I think that's it for me. I mean, I think you've got the summaries, that right?

01:25:33.000 --> 01:25:39.000
Yes, thank you, Jeff. And yes, unsatisfying. But accurate nonetheless.

01:25:39.000 --> 01:25:48.000
So for everyone who joined us today, thank you so much. We're gonna just go through our summary and take a few last questions since we have some time for that.

01:25:48.000 --> 01:25:58.000
But with today's webinars, we talked about how important line use determinations are as from risk assessment to remedy selection under Circle.

01:25:58.000 --> 01:26:13.000
And the also the importance of identifying that anticipated future land use as early as possible through a Hey, very large process that includes community other groups that are going to be affected by the cleanup.

01:26:13.000 --> 01:26:21.000
Also considering reuse and remedy selection, the earlier you can consider reuse the better you can choose remedies that will support that reuse.

01:26:21.000 --> 01:26:33.000
However, if that we use consideration comes later in the process, that's fine as well. Definitely support beneficial reuse where it can be implemented across our federal facility sites.

01:26:33.000 --> 01:26:36.000
With the off-site rules at OSR. Again, the whole point of that is to make sure we're not making future super fun sites.

01:26:36.000 --> 01:26:52.000
We do not want to contribute to present or future environmental problems. And when it comes to permits, for on-site activities, Circle does not require permits for those onsite activities.

01:26:52.000 --> 01:27:03.000
However, the substantive portions of those requirements still need to be met through the circle of cleanup. So Gene, I'd like to check in with you and see if we have any remaining questions.

01:27:03.000 --> 01:27:08.000
Thank you. We do have just a handful of questions. Left and I do want to let the audience know that we have time for questions.

01:27:08.000 --> 01:27:13.000
So if you are in the midst of typing a question in, please go ahead if you weren't.

01:27:13.000 --> 01:27:22.000
Now is the time to get that question in. And we'll wait to see if some additional ones come in, but let me turn to some that are currently in the queue.

01:27:22.000 --> 01:27:29.000
So regarding your on-site disposal cells, do they also have to follow state requirements?

01:27:29.000 --> 01:27:38.000
If those state requirements are considered a then yes, they would have to follow those requirements. And again, it's a substantive portions if there's administrative type of requirements that would be.

01:27:38.000 --> 01:27:55.000
Required through the state requirements. Those would not necessarily apply just the substantive portions. Jeff or Jill, did you want to add to that?

01:27:55.000 --> 01:27:57.000
Okay.

01:27:57.000 --> 01:27:58.000
As I reach for my mute button. Yeah, I just wanted to, I just wanted to support that.

01:27:58.000 --> 01:27:59.000
Yeah.

01:27:59.000 --> 01:28:17.000
Yeah, those and those A. Wars are identified when when the the record of decision process when the record of decision is is put together and so that that's a discussion and and process that's done through the the circling process.

01:28:17.000 --> 01:28:21.000
So by the time that's finished those A. Rars are identified.

01:28:21.000 --> 01:28:26.000
And that's applicable or relevant and appropriate requirements. Sorry, acronyms.

01:28:26.000 --> 01:28:27.000
Thank you. Thank you, Emmy.

01:28:27.000 --> 01:28:38.000
Yeah. Alright, we did have a question that came in earlier as well about indoor air pathways and occupy buildings.

01:28:38.000 --> 01:28:52.000
One of the attendees noted that the federal facilities program does not involve controls to mitigate. A possible complete indoor air pathways for future occupied buildings that they only look at the existing occupied buildings.

01:28:52.000 --> 01:28:56.000
And they were just curious as to why it isn't a reasonable anticipation or anticipated reuse for occupied buildings to be constructed in the future.

01:28:56.000 --> 01:29:06.000
Regardless of your residential or industrial and use.

01:29:06.000 --> 01:29:16.000
I can take this one. I don't agree with the question. I think we do, incorporate that into our institutional controls if it's an area where you think that is going to be building.

01:29:16.000 --> 01:29:22.000
We'll put in, we'll put a, RAO or, action.

01:29:22.000 --> 01:29:29.000
It's a. Control action objective to state that if there is going to build and they have to do some.

01:29:29.000 --> 01:29:46.000
Mitigation to see if we don't know if it is a pathway. So we can say that it is going to be, but we can put language in the language control language that, if there is going to be building that they have to investigate to see if it is the pathway and if it is a pathway that they have to investigate to see if it is the pathway and if it is a pathway that it has to be

01:29:46.000 --> 01:29:57.000
mitigated either through. What the either through remediation or through a. A system in a building system to prevent.

01:29:57.000 --> 01:29:58.000
Okay.

01:29:58.000 --> 01:30:01.000
Human exposure. So we do see that. Yes, Amy.

01:30:01.000 --> 01:30:06.000
Alright, I think the question also, Ja, had some, I was. Not sure exactly what was meant.

01:30:06.000 --> 01:30:27.000
When you do your baseline risk assessment and you're looking at current risk, that's identifying if there is currently now based on the land use that's happening now and unacceptable risk that would trigger the need for a response action, aedial action in that case versus looking at future anticipated land use, which is slightly different.

01:30:27.000 --> 01:30:39.000
So I'm not sure if there was just an overlap in those current. They sign risk assessment for human health versus, Bermuda action objectives and looking at future land use.

01:30:39.000 --> 01:30:47.000
So there might be a little bit of confusion with that unless I'm misreading the question.

01:30:47.000 --> 01:30:55.000
Okay. All right. I don't see any other questions in the queue, but I just want to be sure because we have time with our fabulous instructors.

01:30:55.000 --> 01:30:59.000
That there aren't any other coming in so if you are a member of the audience and you have no additional questions for the speakers.

01:30:59.000 --> 01:31:09.000
Go ahead and say no questions. Put no questions in the Q&A. That's helpful to know that we have met all of your needs.

01:31:09.000 --> 01:31:22.000
And if you're in the midst of writing an answer, go ahead and carry on. For those of you that might be getting ready to ask well wait I what's this about a series or how do I get credit or what about a certificate or wait?

01:31:22.000 --> 01:31:25.000
What we're gonna cover all of that before we close out today. If you have questions about how to get to the materials, we're gonna cover that before we close out today.

01:31:25.000 --> 01:31:42.000
So I'm looking for any content or topic related questions. And without doubt, I see no additional questions is the most common thing in the queue other than thanks for our speakers.

01:31:42.000 --> 01:31:47.000
So, Emmy, I know you've got your contact info here on the slide. I'll let you share some final thoughts.

01:31:47.000 --> 01:31:53.000
Quick, take a quick look to see if any other questions sneak in and then we might start our close out a little early today.

01:31:53.000 --> 01:32:15.000
Alright, well thank you everyone again for joining us for our first webinar offering for 2024 as part of the federal facilities academy as jean mentioned she'll take you through receiving credit for this course as well as if you want to receive credit for the entire 12 courses to receive credit for this course, as well as if you want to receive credit for this course as well as if you want to receive credit for the entire 12 courses to receive a academy certificate of completion.

01:32:15.000 --> 01:32:22.000
But thank you again also to our instructors, Jill and Jeff. Thank you for sharing your expertise on today's webinar and we look forward to seeing you all at the next one.

01:32:22.000 --> 01:32:23.000
Okay.

01:32:23.000 --> 01:32:31.000
Well, thank you so much. I mean, all right, I'm gonna go ahead and swap out of you and call up some quick final slides before we close out today.

01:32:31.000 --> 01:32:42.000
So I will just echo Emmys thanks to all of the presenters, the organizers, the support staff and the nearly 130 individuals who joined us for today's live broadcast.

01:32:42.000 --> 01:32:55.000
If you weren't here in the beginning, I'm going to just provide a few quick reminders about this over overarching, series called the Federal Facilities Academy that will be taking place over the next year.

01:32:55.000 --> 01:32:56.000
There will be a series of 11 webinars that will host live here through the Cleanup Information Network.

01:32:56.000 --> 01:33:06.000
Today was the first one. We'll carry on on March 20 first with another federal facilities academy webinar.

01:33:06.000 --> 01:33:14.000
That session will look at community involvement at federal facilities. So each month will focus on a different topic. Each of these webinars will be recorded in archives.

01:33:14.000 --> 01:33:41.000
So you may register to take them live or you may watch the recorded version. You can receive participant participation certificates for each webinar, but if you're able to do all 11 webinars and you qualify to take a classroom training delivery that will be a 3 day course open to federal regulators, states, tribal governments, if you're able to take and complete that class, if you do everything that's online and that in person 3

01:33:41.000 --> 01:33:57.000
day classroom opportunity, you can receive a special academy certificate. So just to reinforce or visualize that, again, you can take the 11 webinars that are online open to the public you can either take them live online or replay the archive.

01:33:57.000 --> 01:34:09.000
And then if you are a federal regulator, state regulator, our tribal representative, you may take the in person classroom training as a 3 day course and if you're that one you can only take in person.

01:34:09.000 --> 01:34:16.000
And then you can get participation certificates for any of the online sessions that you take, whether you take them live or watch a recorded version.

01:34:16.000 --> 01:34:24.000
And if you're able to do all of the online classes, whether all online, live, all recorded, or some combination of that.

01:34:24.000 --> 01:34:31.000
And then you also qualify and can take the in-person classroom training. You can receive an Academy certificate, knowing that you've completed the entire series of courses.

01:34:31.000 --> 01:34:41.000
There is a flyer which highlights that and a URL on our training exchange website, which I will place in the chats, that will show you where you can find the complete suite of courses in this series and has points of contact and additional information.

01:34:41.000 --> 01:34:57.000
So I'm gonna drop that in the meeting chat now. But with that overview of all of the sessions, let me walk through just a few final reminders for today's session.

01:34:57.000 --> 01:34:58.000
So first I encourage you to visit us at the Cleanup Information Network or Kluen.

01:34:58.000 --> 01:35:06.000
Org. We do list information related to hazardous way site characterization in cleanup. I also send out a free monthly newsletter tech direct on the first of each month.

01:35:06.000 --> 01:35:15.000
We currently have about 43,000 subscribers from all over the world and we're always looking to add more.

01:35:15.000 --> 01:35:22.000
If you'd like to be alerted as soon as free online training opportunities like today's webinar are available, we will list those in tech direct.

01:35:22.000 --> 01:35:31.000
So I encourage you to sign up for that free monthly newsletter. If you have any problems signing up or subscribing to the newsletter you can send an email to me directly at Balan.

01:35:31.000 --> 01:35:36.000
Gene at EPA. Gov and I'll be happy to manually add you to our list serve.

01:35:36.000 --> 01:35:41.000
At the very start of the session, we highlighted that there is a unique seminar homepage.

01:35:41.000 --> 01:36:00.000
It's that same URL that I placed in the chat shown in red on this slide on that seminar homepage we have a whole collection of information sections related to our class, including information about our speakers in their contact info, links to download what we called the participant manual, which includes not only the slides, but very detailed notes and links to resources.

01:36:00.000 --> 01:36:11.000
So I encourage you to download the participant manual for today's session if you haven't. And then we've also included a link to that flyer that highlights all of the courses in the federal facilities academy.

01:36:11.000 --> 01:36:12.000
And then there are individual links to many of the guidance documents, the mappers, the tools, the example sites.

01:36:12.000 --> 01:36:24.000
The videos, the awards, all of those links again are found in a section on related links here.

01:36:24.000 --> 01:36:25.000
What's also here is a section for our online feedback form and we do encourage you to share your thoughts on today's session.

01:36:25.000 --> 01:36:35.000
So for those of you looking for a participation certificate based on attending today's live broadcast, I encourage you to go to the seminar homepage.

01:36:35.000 --> 01:36:45.000
Scroll down to that seminar feedback form, fill out the feedback form, making sure you check the box at the bottom certifying you were here for the entire session.

01:36:45.000 --> 01:36:52.000
And as soon as you submit your feedback, you'll then have access to a participation certificate that you can print out or save for your own records.

01:36:52.000 --> 01:37:00.000
If you happen to host a viewing party at your location and there were other individuals who joined and watched with you at your connection but they didn't register on their own.

01:37:00.000 --> 01:37:09.000
Please share the link to the seminar feedback form. They can each go there. They can fill it out on their own and get their own participation certificate even though they didn't register on their own.

01:37:09.000 --> 01:37:14.000
And today's session was recorded and will be archived publicly on the clue and page so anybody can come back and replay the session.

01:37:14.000 --> 01:37:33.000
If you happen to be one of the lucky people watching the recorded version of this webinar. Right about now in the archive above my head in the upper right corner, there will be a button that will take you to that summon our homepage and straight to the feedback form, you can still share your feedback, making sure that you check the box certifying you watch the entire archive and then you'll still get a certificate.

01:37:33.000 --> 01:37:35.000
Based on your replay of the archive session. Usually takes us about one week or so to get those archives posted.

01:37:35.000 --> 01:37:46.000
So look for a follow-up email which will point you to this homepage and to the feedback form so you can share your thoughts and get a certificate.

01:37:46.000 --> 01:37:50.000
So again, this is the first of a series. Hopefully you'll come back in March when we carry on or you'll join us on a future session.

01:37:50.000 --> 01:37:59.000
And with that, I want to again thank all of the instructors. All of the support staff in the background and each of you for joining us live in today's session.

01:37:59.000 --> 01:38:13.000
We hope that you'll join us on a future clue and webinar. And with that, I'll formally conclude today's live broadcast.