This meeting is being recorded.

00:00:00.000 --> 00:00:00.000
And with that, it is my pleasure to welcome everyone to today's internet seminar. You should be joining us for today's session coming from the Military Munitions Support Services, or M2S2 group.

00:00:00.000 --> 00:00:00.000
Well, we'll be looking at sessions from the stand down where we focus on remedial action.

00:00:00.000 --> 00:00:00.000
Today's seminar has been sponsored by the Army Corps of Engineers, and I'm joined by a fantastic team of presenters and a co-moderator Jeff Brewer, again, coming from the U.S. Army Corps of Engineers.

00:00:00.000 --> 00:00:00.000
I am Jean Balance and I'll be serving as a technical moderator in the background for today's session, joining you from EPA's Technology Innovation Infield Services Division.

00:00:00.000 --> 00:00:00.000
Before I turn the floor over to Jeff Brewer to get things started, I wanted to walk through a few quick housekeeping items to make sure that everyone understands how to participate in today's broadcast.

00:00:00.000 --> 00:00:00.000
For today's seminar, we have created a unique homepage. The URL is shown in red on the slide. You can also access it through the QR code shown on the lower right.

00:00:00.000 --> 00:00:00.000
This is the same website you went to when signing up for our broadcast. It's the same website that I pointed you to and reminder and confirmation emails. That page will be available from today forward.

00:00:00.000 --> 00:00:00.000
The important thing to know about this particular page is that we do have individual sections where if you scroll further down, you'll be able to access the webinar slides or presentation materials. We've already posted all of the content that our speakers will be covering for today's session. I encourage you to visit that website, bookmark it for future reference. If you're looking for resources or copies of the talks, we have posted them here on the seminar homepage.

00:00:00.000 --> 00:00:00.000
We'll be hosting today's broadcast live through Zoom. You'll be able to participate with the free Zoom application or through a browser of your choice.

00:00:00.000 --> 00:00:00.000
Now, when you're checking in online through Kluent to kind of confirm that you're present, you'll see a yellow box on the confirmation check-in screen. And that yellow box will guide you through the final instructions to join us either in Zoom through Zoom in a browser Or if you cannot join through Zoom, there is an optional call online and we'll give you a link to download the materials and simply follow along by phone.

00:00:00.000 --> 00:00:00.000
Please know, regardless of how you're choosing to participate, audio will be available either through your device or through the telephone lines and all participants, no matter how you're choosing to listen, are automatically muted.

00:00:00.000 --> 00:00:00.000
There's no need to look for a microphone icon or a camera icon. We've disabled webcams. We've also disabled your microphones.

00:00:00.000 --> 00:00:00.000
If you have issues with the online or phone audio, check your local volume settings, disconnect from a VPN if you can, but if that doesn't resolve the issue, feel free to use the Q&A to let me know or send me an email and I'll work with you to troubleshoot those problems.

00:00:00.000 --> 00:00:00.000
For those of you that are connecting in Zoom, you'll see a series of icons at the bottom of your screen. I'll ask you now to click the Q&A button right now. A new window should pop open on your screen.

00:00:00.000 --> 00:00:00.000
And go ahead and use that Q&A window to type in a quick reading to our panelists. I'd like you to test the feature out and just let them know hello.

00:00:00.000 --> 00:00:00.000
Let them know where you're joining from or how excited you are to be here for today's presentations. The Q&A will be available throughout our entire broadcast today, and it's the primary way we'll be collecting your questions, comments.

00:00:00.000 --> 00:00:00.000
Or allow you to report technical issues. After each panelist gives a short presentation, we'll have a brief Q&A period with that panelist.

00:00:00.000 --> 00:00:00.000
So I encourage you to submit your question at any point during their talk because we will stop when they are done with the presentation to read questions to that particular panelist.

00:00:00.000 --> 00:00:00.000
You don't have to wait for the Q&A break, but you do need to get those questions in before we jump into their Q&A break.

00:00:00.000 --> 00:00:00.000
Again, we'll try to get through as many as we can in the time that we have allotted today.

00:00:00.000 --> 00:00:00.000
Live closed captioning is available using the CC or transcript icon at the bottom of your screen, and we are recording today's session. I'll provide information in a follow-on email on how you can access the recording or share it with other colleagues.

00:00:00.000 --> 00:00:00.000
And then please stick with me from the very end because I'll walk through a couple of quick reminders, including how you can get a certificate of participation.

00:00:00.000 --> 00:00:00.000
Visually, if you prefer a pictorial layout, again, audio controls will show up in the left in Zoom. The main portion of your screen will have presentation materials with speaker video or speaker information off to the side.

00:00:00.000 --> 00:00:00.000
We do have view controls. You should see it in the upper middle or upper right of your screen to change the size and scale. That CC button will give you captions. And then the all important Q&A.

00:00:00.000 --> 00:00:00.000
Button so you can send in questions. We have many people joining us from California, from Alaska. We've got people from Chicago, from Omaha district down in Jacksonville.

00:00:00.000 --> 00:00:02.000
So, oh, from Seattle. So glad to have you all joining us. Thank you so much for playing along with that Q&A request.

00:00:02.000 --> 00:00:18.000
So with this very brief technical reminders that I have for our session, it is my pleasure to ask Jeff Brewer from the Army Corps to come on camera so that I can turn the floor over to him and he can officially begin today's session. So Jeff, let me spotlight your video and I'll turn the floor over to you.

00:00:18.000 --> 00:00:27.000
All right. Thanks, Gene. Hey, what we're doing this year, my name is Jeff Brewer. I'm with the Army Corps of Engineers Environmental section down here in Huntsville.

00:00:27.000 --> 00:00:32.000
And every year we try to put on some M2S2 webinars, try to get at least two to three in.

00:00:32.000 --> 00:00:45.000
And being that we're starting, we've started back doing the um stand downs, M2S2 stand downs We decided to pull some of our presentations from there For the people that couldn't attend the stand down.

00:00:45.000 --> 00:00:50.000
And so we've got four speakers today. Dj Myers, Jeff Swanson.

00:00:50.000 --> 00:00:59.000
Nancy Heflin and Elise Goggin. They'll be discussing our… presentations from our eyes.

00:00:59.000 --> 00:01:05.000
I'm sorry, remedial action is not our eyes. Goodness, it's one of those days again. Sorry, folks.

00:01:05.000 --> 00:01:13.000
But we're going to try to get one more out. We've had some with the current environment with everything that's going on with the government.

00:01:13.000 --> 00:01:18.000
We've had some issues trying to get the two and second, third one together.

00:01:18.000 --> 00:01:26.000
So just hang with us. We will notify everybody. The same way through email invitations, if we do get the second, third ones.

00:01:26.000 --> 00:01:30.000
With that, I'm going to go ahead and get started. I'm going to introduce DJ Myers.

00:01:30.000 --> 00:01:43.000
He was an OESS. Now he's a program manager. With the Army Corps of Engineers, and he's going to come up and discuss common challenges to implementing the

00:01:43.000 --> 00:02:13.000
Implementing the remedy. I'm sorry. Here we go. Take it away, DJ.

00:07:59.000 --> 00:08:29.000
Yep, we got you.

00:17:04.000 --> 00:17:34.000
Sure. We're looking at the potential RA gap slide.

00:21:19.000 --> 00:21:30.000
All right.

00:21:30.000 --> 00:21:40.000
All right, DJ, we got some questions for you. Let's see here. Is the government required to compensate residents when asked to evacuate?

00:21:40.000 --> 00:22:10.000
Did they evacuate to government provided hotels housing Are these considerations that we need to account for when planning RA actions and funding.

00:22:53.000 --> 00:22:58.000
Next question. For the case of the inhabited building with RA not performed.

00:22:58.000 --> 00:23:13.000
Is there some notification for future owners of the home? Can a future owner have the RA completed?

00:23:13.000 --> 00:23:20.000
All right. For the case of the inhabited building With RA not performed.

00:23:20.000 --> 00:23:50.000
Is there some notification for future owners of the home Can the future owner have an RA completed?

00:24:10.000 --> 00:24:22.000
All right. Next question. Surface mech removal was described as near surface partially buried items to a depth of six inches below ground surface.

00:24:22.000 --> 00:24:52.000
How does surface mean six inches below ground surface? Isn't surface removal digging anything that is protruding or visible from the surface even near surface seems different than surface.

00:25:30.000 --> 00:26:00.000
All right. Did you leave some mech on site? Why not 100% of the site for evaluation or removal.

00:26:01.000 --> 00:26:31.000
All right. Piggybacking on the future landowner question Are there any legal structures in place to attach Restrictive convenience to property where remediation was not completed Assuming nearby RI determined RA necessary for that property.

00:26:42.000 --> 00:26:46.000
How much time we got, Gene?

00:26:46.000 --> 00:26:49.000
You could probably take one more question.

00:26:49.000 --> 00:26:57.000
All right, let's see. Do you plan for a certain percentage of owners refusing to evacuate?

00:26:57.000 --> 00:27:09.000
How do you convince management that planning for this is acceptable?

00:27:09.000 --> 00:27:39.000
Do you plan for a certain percentage of owners refusing to evacuate How do you convince management that planning for this is acceptable?

00:28:38.000 --> 00:28:49.000
All right. If I did not answer any of these questions, we will be getting a copy of these questions that we can send out to you, hopefully get your answers later.

00:28:49.000 --> 00:28:57.000
Appreciate it, DJ. You did a great job. Thank you.

00:28:57.000 --> 00:29:04.000
All right, which will bring us up to our next presentation. I believe that's Mr. Swanson.

00:29:04.000 --> 00:29:07.000
Or is it Nancy?

00:29:07.000 --> 00:29:09.000
Our next presentation should be Nancy.

00:29:09.000 --> 00:29:23.000
All right. Sorry, I should have grabbed the… The gen in front of me. All right. We got… Miss Nancy Heflin, she's uh works with the… Army Corps of Engineers.

00:29:23.000 --> 00:29:34.000
And down here in Huntsville. And she's going to be presenting records we need in the record of decision.

00:29:34.000 --> 00:29:39.000
One second, share my screen.

00:29:39.000 --> 00:29:45.000
All right. I think it's up. All right. Well, thanks for joining everyone.

00:29:45.000 --> 00:29:58.000
I have about 20 years experience in MMRP and I just wanted to change of pace from contractor work. So I've been working for The Huntsville Design Center.

00:29:58.000 --> 00:30:03.000
Sorry, the Huntsville Center Military Munitions design center since about November of 2023.

00:30:03.000 --> 00:30:20.000
So while I was preparing for this presentation, I gave the same presentation at the M2S2 stand down. And when I was looking through it again, really the thing that jumps out at me is the main picture the what we need to think about is begin with the end in mind.

00:30:20.000 --> 00:30:37.000
So I'm talking about a record decision, but almost everything I'm talking about are things that we should have captured earlier, ideally. So these things could have been in an RI, CSM or added in the CSM and the FS report or during the alternative

00:30:37.000 --> 00:30:51.000
Evaluation. So don't think I'm only covering record decision here. A lot of this information is stuff that We want to check that we got it by the record decision because that's the end of the phase and we're moving forward.

00:30:51.000 --> 00:30:56.000
But a lot of it, ideally we should have gotten to already.

00:30:56.000 --> 00:31:10.000
So a couple of context references. The requirement for the rod and the circle process, of course, is spelled out in the NCP. And there are actually details in that NCP to tell you what you're required to do legally.

00:31:10.000 --> 00:31:37.000
For our process. The EPA, came out with a guide guide to preparing super fund proposed plans requisitions and other remedials selection decision documents, that is actually still used right that it's old from 1999 but A lot of it is still valid in its use as a reference for rods. The dirt manual from 2012

00:31:37.000 --> 00:31:49.000
Is really mostly just a repeat of the NCP, but one piece of information that I got out of that that was kind of newer, more recently new to me is that the difference between a decision document and a record decision.

00:31:49.000 --> 00:32:07.000
So decision document is generic and it could be like for a TICRA or any kind of place where we're going to do a removal action But the rod applies specifically to specifically the decision at the end of the RFS process. So, you know, when you go through

00:32:07.000 --> 00:32:16.000
Your ri your fs your proposed plan and your rod to come up with your remedial action plan, that's called a rod, not a DD.

00:32:16.000 --> 00:32:24.000
So I know in the past we've all been mostly just using dd But we should try and move forward with that distinction.

00:32:24.000 --> 00:32:37.000
And then the last reference here is the FUDS handbook. And I think it's a really good place to start. It's got an outline for your record decision And some good information.

00:32:37.000 --> 00:32:48.000
I generally start with a handbook. To write a record decision and then if there's a part that I'm not sure about what needs to go in it, then I'll reference back to that EPA document.

00:32:48.000 --> 00:32:54.000
To see exactly what they expected in that. That portion of the document.

00:32:54.000 --> 00:32:59.000
So, um. Let me get back, cut ahead.

00:32:59.000 --> 00:33:12.000
This is the outline that is in the FUDS handbook. So if you go to worksheet c1 In the FUDS handbook, it's going to give you a little blurb about each section, what goes in those sections.

00:33:12.000 --> 00:33:21.000
One important detail i wanted to Sorry, I'm going the wrong direction, point out is that really part one is your executive summary.

00:33:21.000 --> 00:33:37.000
You shouldn't need a separate executive summary. I would say that that's going to be PDT specific. I know I just did one that did have an executive summary and they ended up using that executive summary to provide through command for signature. So it was helpful to have it

00:33:37.000 --> 00:33:47.000
But in general, you really part one as well. Is supposed to be the executive summary and then all the detail goes into the other parts.

00:33:47.000 --> 00:34:01.000
So real quick, we're going to go through mostly focusing on a couple sections in the rod and that is the the what we'll also talk about the remedial action objectives, the description of the alternatives.

00:34:01.000 --> 00:34:10.000
Selected remedy and then a little touch on the documentation of significant changes from the preferred alternative of the PP.

00:34:10.000 --> 00:34:16.000
So I will… get into that.

00:34:16.000 --> 00:34:27.000
So the first thing I want to talk about is what is the difference between the remedial remedial action objectives which are remediation goals and cleanup levels.

00:34:27.000 --> 00:34:32.000
I think this was confusing for me even when I first started putting these slides together.

00:34:32.000 --> 00:34:43.000
On how to describe this. Important thing is to remember that your remedial action objectives and those goals are outlined before we ever talk about what our alternatives are going to be.

00:34:43.000 --> 00:34:52.000
So you shouldn't see a lot of detail in RAOs that are very specific to whatever remedy you're going to select.

00:34:52.000 --> 00:35:11.000
But contrary to that, you're going to have cleanup goals in your remedy that are very specific to the remedy and they are measurable and how we measurable can determine that we achieved the remedial action objective. So recently, I worked on an in-house rod and

00:35:11.000 --> 00:35:18.000
The way we handled our rios is We had some texts, of course, to describe it and introduce the different pieces, but mostly it was a table.

00:35:18.000 --> 00:35:32.000
And so that table included the contaminated media. So it was the MEC. What MEC do we have on site? Well, that was a really long list for this site. So we had a separate table of just the mech.

00:35:32.000 --> 00:35:46.000
Say these are the munitions that we expect to see at the site Then we had our assessment areas, which everybody should hopefully be familiar with from a lot of the discussions and presentations on the risk management methodology.

00:35:46.000 --> 00:36:04.000
So… You've got all those different areas, then you're listing your receptors and your exposure pathways and your depth of exposure. Depth is important to get in there. But remember, you're not listing your depth of the cleanup that you're going to put in your alternatives, you're listing your depth of exposure so

00:36:04.000 --> 00:36:15.000
Where are these receptors exposing being exposed to MEC. And our radiation goal Because we've got everything built into that table, it's pretty simple.

00:36:15.000 --> 00:36:22.000
It was mitigate potential exposure pathways such that those activities no longer present an unacceptable risk.

00:36:22.000 --> 00:36:37.000
So essentially. The REO is our big picture goal. We don't want to have people exposed to unacceptable risk. And then the cleanup goals are going to say, well, how do we measure that we actually achieved that?

00:36:37.000 --> 00:36:58.000
So. I think hopefully that's clear on the difference. If not, ask a question One thing to keep in mind, I know that a lot of i've seen some where we have written that you know the selected remedy is going to

00:36:58.000 --> 00:37:12.000
Achieve acceptable risk conditions or something along those lines where we're trying to link The cleanup goal back to the RMM and we shouldn't be doing that essentially The rod is designed so that we say, here's what we want to achieve

00:37:12.000 --> 00:37:19.000
And then when we get to the actual Alternative, we're describing how do we measure that we achieved it?

00:37:19.000 --> 00:37:24.000
So when we have a signed rod, we have all as a team and the commander who signed it.

00:37:24.000 --> 00:37:29.000
Have agreed that if we do what it says in the selected alternative.

00:37:29.000 --> 00:37:53.000
We have achieved the RAOs based on the current conditions and the reasonably anticipated future conditions. So we're looking at our exposure pathways we're deciding, okay, if we do this thing then we will have achieved this goal of preventing unacceptable risk. So after

00:37:53.000 --> 00:38:02.000
You know remember that the RMM is not really meant It was never built to measure the success of an RA. It was always built to determine is there risk?

00:38:02.000 --> 00:38:09.000
And after that, you really can't use it. You can't just put in, oh, now we've cleaned it up, so we'll take them out and we'll have this new evaluation.

00:38:09.000 --> 00:38:14.000
It was never intended for that. So please avoid that in the future.

00:38:14.000 --> 00:38:31.000
Moving into the next slide. Let's see. So some of the issues that we've run into on records of decision, these next couple of slides, I'm just going to go through a bunch of different things that we've had problems with. So sometimes we've had vague cleanup criteria

00:38:31.000 --> 00:38:47.000
Or they're unattainable. I ran into a site where it was an old rod, of course, and we were trying to clean it up to three feet. Well, you can't do that with the remedy that they described in the rod, right? We can't achieve a three fit removal for the munitions on site. So that was unattainable.

00:38:47.000 --> 00:38:55.000
Some of them don't explain how we're going to judge when we get to response complete.

00:38:55.000 --> 00:39:01.000
What do we use? What's measurable statement that we can evaluate?

00:39:01.000 --> 00:39:10.000
Vague or non-existent loose descriptions. You don't want to just say we're We're doing Luke's and we'll get into that a little bit later in another slide.

00:39:10.000 --> 00:39:29.000
Let's see, we don't explain. Where the errors, how we're compliant with the errors We also need to comply with the FUDS policy and the DoD policy. So DoD policy says we have to maximize use of digital geophysical mapping. The FUDS policy says we need to evaluate

00:39:29.000 --> 00:39:38.000
Using the advanced geophysical classification. So depending on what type of project you're on, you have different requirements. But I think in general.

00:39:38.000 --> 00:39:45.000
People are going to expect to see AGC alternatives on every every uh option or every rod.

00:39:45.000 --> 00:39:58.000
So then some of the other issues we've had with other issues remedial footprint. It's not clearly defined. Maybe we say over the entire MRS. But it really doesn't address the fact that there's a highway running through the middle of the MRS and we can't

00:39:58.000 --> 00:40:13.000
Really clean up below a highway or a road or existing buildings. So you have to be careful that when you say you're going to treat the entire MRS You mean the entire MRS and that you don't have any places that you can't get to.

00:40:13.000 --> 00:40:20.000
And we'll get into that a little bit more. Where they don't account for sensitive habitats.

00:40:20.000 --> 00:40:29.000
Let's see. So when we're talking about the surface and subsurface mech removal.

00:40:29.000 --> 00:40:36.000
Let's talk about how you know that you've achieved the remedy. So we need specific cleanup criteria. So we want to say.

00:40:36.000 --> 00:40:43.000
We want to remove MAC removal would be to a depth of 18 inches.

00:40:43.000 --> 00:41:00.000
And then a thing that we've been adding in is or to the limit of detection for smaller mech items. We know we can't get a small munitions item to 18 inches The design is that our goal is let's get to 18 inches. We understand that we can't get to 18 inches for every munition item.

00:41:00.000 --> 00:41:07.000
And we make that clear in the rod so that when we do the remedy that it isn't a new concept.

00:41:07.000 --> 00:41:30.000
So on the other example I was talking about earlier, we had Not in the RAOs, but later in the report where we're talking about the actual remedy, which was the remedy maybe the third alternative we get into where we're going to do is surface and subsurface removal. We said these are the expected depths that we can detect these munitions.

00:41:30.000 --> 00:41:43.000
We also said if different instruments are used or if there are different site conditions that may vary But we didn't say we're just going to clear to 18 inches because that would be disingenuous. We really can't do that for all munitions types.

00:41:43.000 --> 00:41:48.000
At this site, I should say that some you may be able to.

00:41:48.000 --> 00:42:00.000
Let's see, we need to specify where the remedy will be implemented. I mentioned this before, so you've got to bring up those exception areas. If we've got buildings and roads or large trees.

00:42:00.000 --> 00:42:05.000
And we're not going to dig up the building. We're not going to remove the roads. We're not going to remove the big trees.

00:42:05.000 --> 00:42:16.000
So therefore, there may be MEC below them. Then we have to say that in the rod so that it isn't questioned later on whether we achieved response complete.

00:42:16.000 --> 00:42:31.000
And then, um. Be sure to specify the limitations. So we want to make sure that the person who reads this rod understands that we already knew that there were going to be munitions that get left behind, that we can't clean them all up

00:42:31.000 --> 00:42:53.000
And that we're using Luke's to manage that residual hazard so make sure it's stated, right? We don't want a reader in five, 10 years when they go to do the five-year review Just say, well, I don't know if they understood that that was the case. And so maybe this isn't protective because they didn't make it clear that there would be

00:42:53.000 --> 00:43:13.000
So state your limitations, get it documented in the rod The CSM has a huge impact on everything right a lot of this stuff when you're doing the ri it's easy it's you talk about it, but you avoid it, right? So an RI, you're doing transects, you've got archaeological cultural resources

00:43:13.000 --> 00:43:26.000
Somebody goes out and maps them and you're like, okay, well, we're going to go around that or we're not going to go through this sensitive habitat And you can still do your ri But when you get to your RA and you have to cover the whole site.

00:43:26.000 --> 00:43:45.000
And you've got something really significant cultural resource that you can't blow something up next to, you've got to document that. So in the RA, you need to make it clear that you have exception areas to to get this like, you know, documented so that

00:43:45.000 --> 00:43:58.000
It's not a problem that we missed. The mech in that area potentially. Wetlands talk about land uses, vegetation, how it may impact the selection of equipment, slopes, roads, all these things.

00:43:58.000 --> 00:44:08.000
We really need to make sure that we understand our CSM And if you've gotten to the RA, or sorry, you've gotten to the rod and these things are not clear.

00:44:08.000 --> 00:44:15.000
Add them in. So don't think that, well, the RI didn't cover it, so it's not important. The CSM is a living document.

00:44:15.000 --> 00:44:22.000
We all understand that we're learning every day about new things and technology has been changing. So as things change.

00:44:22.000 --> 00:44:27.000
As we learn more, we should be updating the CSM throughout this process.

00:44:27.000 --> 00:44:40.000
And then again, list the exception areas. Let's see. So land use controls. Here's the same kind of thing. How are we going to determine whether we've achieve response complete.

00:44:40.000 --> 00:44:46.000
We don't want the rod to be a land use controls implementation plan. It's not the work plan that says this is how you're going to do everything.

00:44:46.000 --> 00:44:54.000
But if you're going to use pamphlets for your loops, then say you're going to use pamphlets. How are you going to distribute them? Are they going to be mailed?

00:44:54.000 --> 00:45:11.000
To all the landowners in the county or are they going to go to the landowners only in the MRS? Or, you know, there's a lot of different things that your team who's riding this rod is deciding what is acceptable to achieve the RAOs, and you've got to be clear on that.

00:45:11.000 --> 00:45:21.000
To make sure that that's documented. If you're going to have meetings to go over the three R's, how often are they going to happen?

00:45:21.000 --> 00:45:37.000
If you're going to have signs, you don't have to say we're going to have this many signs, but say we're going to include a sign at the main park entrance and we're going to include assign the three parking areas or we're going to put a sign every 200 feet along the entire boundary. There's a lot of differences

00:45:37.000 --> 00:45:47.000
That could come up. So the people deciding this remedy is protective need to define a little bit more about what it is that you're doing with the Lukes.

00:45:47.000 --> 00:45:56.000
Again, training for who like what what's the audience of the pamphlets? What's the audience for them for all of that.

00:45:56.000 --> 00:46:14.000
And then, for example, if your audience is just the landowners, that might not be that big of a task but if you have a public site that's visited by everybody in the county every other weekend, then you may have a much bigger audience and that's something that needs to be captured in your rod.

00:46:14.000 --> 00:46:18.000
Another thing to think about is who will implement the loop.

00:46:18.000 --> 00:46:34.000
For example, we had a site that the landowner is going to put the pamphlets in their you know hut where they sell permits. So we are going to provide them, but really the landowner is going to be handing them out and we need that documented and everybody's on the same page and agrees that

00:46:34.000 --> 00:46:45.000
How that's going to be done. Munitions constituents that one seemed it's like so much easier than the others to determine whether you've actually done it.

00:46:45.000 --> 00:46:53.000
But you need to know what are the COCs. It's not every chemical that you looked at in the RI. It's only the COCs that came out of the risk assessment.

00:46:53.000 --> 00:46:59.000
Specify which cleanup levels you're using, what are you cleaning up to? Is it residential? Is it industrial?

00:46:59.000 --> 00:47:15.000
What state levels are included, whatever, however that's done. And then also What type of sampling is going to be required to confirm your complete. So if you're doing a removal and you're excavating what do you need to do to say, yes, we got it all.

00:47:15.000 --> 00:47:21.000
What type of sampling. Get that in your rod so nobody's questioning it. It doesn't have to be every single detail.

00:47:21.000 --> 00:47:29.000
But enough to reduce questions. In the future when we're trying to implement.

00:47:29.000 --> 00:47:46.000
So another thing to think about is Is it implementable, right? So a lot of these are old or maybe the fs was written six years ago and you're just getting to the rod stage And you're like, you know what? We really can't do

00:47:46.000 --> 00:47:52.000
We can't do what it said. Let's think this through. Let's stop.

00:47:52.000 --> 00:47:58.000
And don't move forward to an RA and just keep pushing something that can't be done.

00:47:58.000 --> 00:48:09.000
If we can't do AGC, can we do DGM? Can we document that analog everybody says like, oh, we can't do analog. Well, you can't do analog without getting approval to do analog.

00:48:09.000 --> 00:48:21.000
But one way to get approval to do analog is you get it in the rod. So if you have in there that you've got this one area is wetlands and the only way you can get in is on foot and you're going to do analog in that area.

00:48:21.000 --> 00:48:27.000
Then you're going to have to document that. And by getting it in the rod, you've got signature on it for approval.

00:48:27.000 --> 00:48:33.000
Save some time in going back to try and get that later.

00:48:33.000 --> 00:48:48.000
And then let's see, what about utilities? Are there like we had a site where there was a road and The landowner was like, well, you can clear the whole site, but don't mess with the road because we're afraid it might cause erosion or do something

00:48:48.000 --> 00:48:57.000
To the slope along the side of the highway and you can't go there. So we need to talk about those things before we get and get it documented in the rod.

00:48:57.000 --> 00:49:08.000
Are there other agencies involved in, like we talked about the Lukes, the pamphlets, we need to document their willingness to participate in that.

00:49:08.000 --> 00:49:29.000
I know DJ had talked about people that won't that won't leave like do we have alternatives If we can't do evacuations for demo lake are there alternative are there the open face barricades and things like that and make sure that that's discussed that we're going to take that step where we're not.

00:49:29.000 --> 00:49:34.000
Because you don't want that to be a new cost that comes out in the RA that wasn't accounted for in that.

00:49:34.000 --> 00:49:44.000
Rod estimate. And then, you know, of course, do they comply with policy? We've sort of already talked about those.

00:49:44.000 --> 00:49:56.000
So I'll skip that. And then the thing is You know, just because it doesn't say I mean, this is my opinion. If your team is really struggling and you don't know the answers to some of these things.

00:49:56.000 --> 00:50:12.000
And you're getting ready to put a rod together then talk to your COR and say, you know, I think we need a site visit. There was no site visit in the contract but It seems like you guys are really wanting a lot more than what we can do from our computers and ask for a site

00:50:12.000 --> 00:50:19.000
See if you can get that added on or something. And if it's not under contract, you know.

00:50:19.000 --> 00:50:28.000
Teams that you say put that in there. Put a site visit as an optional task on your contract when you're going into these things because it might save some headaches down the line.

00:50:28.000 --> 00:50:38.000
I'm trying to implement the RA. And then do we need it? Should we exclude it? So another thing that came up, we often, at least on our older ones, we're always saying.

00:50:38.000 --> 00:50:48.000
We're going to do a surface and subsurface mech removal. Well, unless you have a lot of debris on the surface that would impact your ability to do geophysics.

00:50:48.000 --> 00:51:05.000
You may not need a full surface removal because you're going to get those MEC items when you do the subsurface removal Presumably. So you could have less quality control for a sweep, for example, rather than a surface removal, it might be able to save a lot of money

00:51:05.000 --> 00:51:11.000
If you change that in the rod to say, you know, where we're doing subsurface removal.

00:51:11.000 --> 00:51:26.000
If it's below whatever it's below the geophysicists say it needs to be for respect to impacting the detection then you could do a sweep and clean up the debris rather than a full QAQC surface removal.

00:51:26.000 --> 00:51:35.000
And then, um. Don't just jump to exception areas for everything. Think about other options.

00:51:35.000 --> 00:51:50.000
We can't go to this area because of whatever reason, but we could do it if we use a different instrument and maybe we need to put that in the rod and get permission like analog to get that rod signature.

00:51:50.000 --> 00:52:03.000
And then let's see. Okay, so if you've gotten all the way to your rod and you're realizing that something's not going to work, right? There is a way to get that fixed.

00:52:03.000 --> 00:52:10.000
So there's a section in the raw that says documentation of significant changes From the preferred alternative of the PP.

00:52:10.000 --> 00:52:20.000
So you've presented it to the public. You've had your meeting. You said this is what we're going to do. And you start going through the process and people start reviewing the rod and they're like, you know.

00:52:20.000 --> 00:52:24.000
We really need to add this thing or we need to tweak this thing.

00:52:24.000 --> 00:52:43.000
There's a section in there to talk about that. Make sure that you've talked with office counsel on your PDT and that you don't have to do a revised pp sometimes you can get away with an edit and it doesn't require going back and doing a new proposed plan public meeting and other times it's significant enough that you have to do

00:52:43.000 --> 00:52:47.000
A proposed plan public meeting to be able to make that change.

00:52:47.000 --> 00:53:04.000
So the point is. It's better to get this stuff right than repeat it later and have to deal with a lot of ESD's rod amendments or reas So since we've learned a lot the last few years i mean Since day one of this program, we've always been learning

00:53:04.000 --> 00:53:13.000
Take the time to take the time pause and think through what's going on in your projects and if we need to update some things or change things along the way.

00:53:13.000 --> 00:53:18.000
And try not to just push things forward because that's what the FS said.

00:53:18.000 --> 00:53:24.000
Etc. So any questions?

00:53:24.000 --> 00:53:27.000
All right, we got some questions for you, Nancy. Hope you're ready.

00:53:27.000 --> 00:53:28.000
I'll try.

00:53:28.000 --> 00:53:36.000
Okay, the first one is actually a combination of two questions. They kind of ask the same thing. So I'm going to go ahead and read them both off.

00:53:36.000 --> 00:53:41.000
First one was, do you have a standard rod template used for mech sites.

00:53:41.000 --> 00:53:57.000
And the second one, I believe, goes with it is, do you have a well-written sample rods that you can point staff to looking for best of type examples for new staff They seem to learn best through examples.

00:53:57.000 --> 00:54:14.000
So I would say not yet. From what I've heard, we're still piecing together exactly what is good and there's some good Some that have good parts in one way and not good in the other. So I think that I've heard that EMCX is working towards trying to get something

00:54:14.000 --> 00:54:19.000
But not just yet.

00:54:19.000 --> 00:54:27.000
All right. Good. The difference between the decision document and the rod be restated again?

00:54:27.000 --> 00:54:45.000
Okay, so a decision to document is a generic term for any kind of decision to do removal. So it could be a documented document that says we're going to do a tikkra. It could be a document that says we're going to do an end tikra.

00:54:45.000 --> 00:54:54.000
It could be, I'm not sure of other examples but it's It's not necessarily the one that comes after your FS and your proposed plan.

00:54:54.000 --> 00:55:01.000
It can be a side a side removal action, not the remedial action.

00:55:01.000 --> 00:55:31.000
So when you're doing the remedial action. And you're following the circle of standard process and you haven't stepped off on these side requests, that's when you have a rod so it's I would say it's when you've got your FS proposed plan and you're moving into the next document it's the rod a generic term for any decision document is the DD.

00:55:32.000 --> 00:55:33.000
Awesome.

00:55:33.000 --> 00:55:42.000
All right. Oh, I like this one. Has the army started exploring the use of AI to write or review rods Our agency is looking to use AI to write these documents faster.

00:55:42.000 --> 00:55:51.000
I don't know. I'm not sure that I'm aware of. I wouldn't say that I know what everyone's doing.

00:55:51.000 --> 00:55:56.000
I guess I'm not the right person to answer that question.

00:55:56.000 --> 00:55:57.000
Awesome.

00:55:57.000 --> 00:56:16.000
Okay. Next one here. Do you need a formal agreement from other organizations that will be distributing education materials What level and form of Commitment is needed from the distributing organization to include the distribution in the rod.

00:56:16.000 --> 00:56:33.000
I also don't know the answer to that. I would talk to office counsel and make sure they're comfortable with it. I mean, the The issue is we want to avoid one that people don't understand what their role is. We want to avoid anybody making assumptions.

00:56:33.000 --> 00:56:49.000
So if you can get it documented in maybe your institutional analysis report that they're willing to do something and then You're documenting in the rod that they've agreed and you have it in meeting notes or some kind of documentation

00:56:49.000 --> 00:56:57.000
That would be my first go-to, but I really think you'll have to talk to your PDT's office counsel on what their expectations are for that.

00:56:57.000 --> 00:57:03.000
But we really don't want things to just get assumed and really not discussed.

00:57:03.000 --> 00:57:21.000
And it may be that you need to go higher than just the person you're talking to on your project, because maybe that's currently the guy in charge of you know the booth but you should be talking to his boss or the other boss to make sure that they're willing to accept that moving forward that when he quits and the next guy comes in

00:57:21.000 --> 00:57:29.000
That they're also going to be taking those pamphlets and telling us when they're out and and putting them on their display.

00:57:29.000 --> 00:57:44.000
All right, next one here. Can you offer insight on how detailed the land use controls description should be in regard to the inaccessible areas described in the rod.

00:57:44.000 --> 00:57:46.000
Read that one more time.

00:57:46.000 --> 00:58:02.000
All right. Can you offer insight on how detailed The land use controls description should be in regard to the inaccessible areas described in the rod.

00:58:02.000 --> 00:58:18.000
So you're specifically, so in general, what I've seen is that your Lukes are going to be for the whole site right there Considering that But that's with its educational awareness there's other things but generally, you know, you're you're luke

00:58:18.000 --> 00:58:27.000
Plan is going to be For this site, we're going to do these things. And the details that I laid out, like what you're going to do.

00:58:27.000 --> 00:58:38.000
Generally, the scope of it not just saying we're going to use signs roughly what the point of those signs are or how many you expect or where the area is going to be.

00:58:38.000 --> 00:58:52.000
Now, if you're going to put in a fence around an area, say you have an exclusion area that is and you're going to put a fence in, whatever the situation is that you need to include to make sure that when they finish the RA,

00:58:52.000 --> 00:59:08.000
And they've implemented those loops. Everybody's like, yep We did what we said we'd do in the rod, so therefore this is protective. It meets CROs because we wrote out enough detail in the And the rod just describe what we were going to do. And we did that. That's really what we're trying to avoid is

00:59:08.000 --> 00:59:13.000
Is getting to the end and then having a regulator say, no, that's not what I expected.

00:59:13.000 --> 00:59:19.000
And I don't think that you've achieved. Your objectives.

00:59:19.000 --> 00:59:26.000
All right. Last question. And actually, this is for elise a couple of geophysics questions popped up in here.

00:59:26.000 --> 00:59:31.000
First one is please clarify the difference between DGM and AGC.

00:59:31.000 --> 00:59:32.000
Awesome.

00:59:32.000 --> 00:59:52.000
And also… Can you give example of an AGC DGM or non-AGC DGM where you would not necessarily require a surface clearance. I always assumed it wasn't just for anomaly reduction but also for safety of DGM operators.

00:59:52.000 --> 00:59:56.000
Sure, can y'all hear me? Just making sure I'm off mute.

00:59:56.000 --> 00:59:57.000
Gotcha.

00:59:57.000 --> 01:00:10.000
Okay. So DGM is digital geophysical mapping. Agc is a component of that. So AGC is advanced geophysical classification. I think as Nancy pointed out.

01:00:10.000 --> 01:00:31.000
Fuds requires the maximum use of AGC, which is, like I said, a component of DGM. We would refer to other types of DGM as non-AGC DGM in today's world so Hopefully that clarifies it. Agc is capable of classifying the anomalies, whereas DGM is typically

01:00:31.000 --> 01:00:35.000
Only capable of detecting them. So that's the first part of that.

01:00:35.000 --> 01:00:45.000
Question. And then the second part I think was related to kind of a surface sweep. So surface sweeps are typically a safety component.

01:00:45.000 --> 01:01:00.000
I think where Nancy was going in regards to the defining the difference between a surface sweep and a surface removal is that a removal has a different meaning for us. And so that would be a component of the remedy.

01:01:00.000 --> 01:01:08.000
And that would require a greater level of quality control, such as seeding, for example.

01:01:08.000 --> 01:01:15.000
Whereas a surface sweep can be done to ensure that the surface is free of explosive hazards.

01:01:15.000 --> 01:01:31.000
And to facilitate additional work on the site. So we would do that surface sweep as a safety precaution, but we wouldn't need to go through the process of employing all of those quality control requirements. So hopefully that answers those questions. Thanks.

01:01:31.000 --> 01:01:40.000
All right. Thanks, Elise. That's all the time we have on this presenter. Thanks, Nancy. Thanks, Elise. Both did a wonderful job.

01:01:40.000 --> 01:01:50.000
And we'll keep moving on to our next presentation. Mr. Jeff Swanson, he is with the Hazardous Materials Division.

01:01:50.000 --> 01:02:05.000
Of the Colorado Department of Public Health and Environment. I got to say one thing. One thing I like about Well, Jeff, he's presented with us before, and it's always good to get people outside the Corps of Engineers up here presenting.

01:02:05.000 --> 01:02:11.000
And hopefully that's exactly what he's talking about. His presentation is regulatory perspective on rods.

01:02:11.000 --> 01:02:18.000
From MRP. So… We're actually getting an outside agencies perspective on these things.

01:02:18.000 --> 01:02:20.000
Take it away, Jeff.

01:02:20.000 --> 01:02:29.000
Thanks, Jeff. And you're going to get a bonus because it's not only going to be a regulatory agency talking about their perspective.

01:02:29.000 --> 01:02:43.000
But sharing a lot of the… the things that we've learned in how bad we've screwed up in records of decisions along the way and the hard lessons we've learned in doing that.

01:02:43.000 --> 01:02:50.000
So hopefully it's… as an educational and entertaining.

01:02:50.000 --> 01:03:05.000
To start off. We all know a record or decision is basically just the document that selects the remedial action that we're going to go out and implement on our site.

01:03:05.000 --> 01:03:18.000
But when you start looking at a record of decision It really has… four different four different uses.

01:03:18.000 --> 01:03:24.000
It's a legal document. So for the lawyers in the room.

01:03:24.000 --> 01:03:33.000
That recorder decision needs to certify that the Remedy has been selected following the CERCLA process.

01:03:33.000 --> 01:03:41.000
And that we're good to go from that perspective. That rod is also a summary document.

01:03:41.000 --> 01:03:52.000
It's a summary of all the technical information and rationale to support our our cleanup decision from our administrative record.

01:03:52.000 --> 01:04:18.000
It's a technical document. In that the information necessary to determine and implement the remedy is in there and the description of that of that remedy is in there and that's that's going to be the main focus of uh my talk today. It's also a key public

01:04:18.000 --> 01:04:45.000
Public communication tool. This is the document that The public is going to be directed to in terms of What remedy did we select and What contamination are we seeking to clean up and the rationale for that?

01:04:45.000 --> 01:04:53.000
So looking at the rod as a technical document. What are the important pieces? Remedial action objectives.

01:04:53.000 --> 01:05:00.000
And Nancy talked about those. I'm not going to get into a lot of detail about remedial action objectives.

01:05:00.000 --> 01:05:07.000
Here, there's been a lot of talks about them and there's a lot of work going on in quite frankly, improving them.

01:05:07.000 --> 01:05:13.000
But think of that as what's the What's the remedy trying to accomplish?

01:05:13.000 --> 01:05:21.000
It's got to have the description of the alternatives. What are the components of the remedy? How did we piece those together?

01:05:21.000 --> 01:05:30.000
How do we think that placing those those putting those pieces What do we think the expected outcome is?

01:05:30.000 --> 01:05:37.000
So that we can evaluate those and finally select a remedy. And that remedy selection piece is critical.

01:05:37.000 --> 01:05:45.000
It's got to have the rationale for selecting the remedy. A good description of that remedy.

01:05:45.000 --> 01:05:51.000
Of course, a summary of the costs that we are estimating that will take.

01:05:51.000 --> 01:05:59.000
And then the outcome when we're done. And that's going to be important to the people that live there to know.

01:05:59.000 --> 01:06:15.000
What we expect to be leaving behind. So again, remedial action objectives it's uh To me, I think of the remedial election objectives as setting the bar for each component of the remedy.

01:06:15.000 --> 01:06:23.000
Is it surface clearance? Is it subsurface clearance? Or different land use controls, whatever those are.

01:06:23.000 --> 01:06:29.000
What are we trying to accomplish? What is our cleanup goal?

01:06:29.000 --> 01:06:38.000
We've got to have in our record of decision a clear statement of those specific remedial action objectives.

01:06:38.000 --> 01:06:44.000
The more we can have those remedial action objectives tied to each remedy component.

01:06:44.000 --> 01:06:56.000
Including the basis and rationale for that. And what it really comes down to it, it's how are those remedial action objectives going to address the risks at the site?

01:06:56.000 --> 01:07:01.000
And when you finish the remedy and you're looking back to demonstrate protectiveness.

01:07:01.000 --> 01:07:12.000
Having those clear discussions and having that all in the rector decision is absolutely critical.

01:07:12.000 --> 01:07:22.000
Description of alternatives. You'll see in a good record decision, there's going to be brief descriptions of each of the remedial alternatives.

01:07:22.000 --> 01:07:33.000
Usually a bulleted list or a table and that um that 1999 guidance has a great table in there of how to do that.

01:07:33.000 --> 01:07:41.000
Because you really want to focus on What are those remedial alternatives? What are the common elements in them?

01:07:41.000 --> 01:07:48.000
And what are the outcomes? What are the available land uses?

01:07:48.000 --> 01:08:01.000
When you've implemented each of those different alternatives. If it's a surface only clearance alternative, what are the available land uses if it's some combination of surface and subsurface.

01:08:01.000 --> 01:08:09.000
Because those are the things that are going to be critical at the end in What did we leave behind and are we protective?

01:08:09.000 --> 01:08:28.000
And you've got to do that down the media level, come up with specific metrics of What are the impacts and benefits of each of those alternatives?

01:08:28.000 --> 01:08:40.000
Going through those kind of quickly. I think the part that we really need to focus on in our records decision Are these remedial action components?

01:08:40.000 --> 01:08:55.000
In a general sense, you've got treatment technologies And you want to describe each of those generally. You don't want to be too specific so that you're locked into a specific type of technology.

01:08:55.000 --> 01:09:10.000
You need to be specific enough that that you know what's going to be implemented But you don't want to have to go back and change your record decision if you selected brand A instead of brand B.

01:09:10.000 --> 01:09:20.000
For munitions it would be If you're going to do a remedy with AGC, you want to put that into the description.

01:09:20.000 --> 01:09:29.000
But you don't need to specify whether you're going to do queued or one pass or whatever the next GWiz, AGC is.

01:09:29.000 --> 01:09:40.000
For land use controls. This is probably the part that I've seen and I've been screwed up as much as anybody.

01:09:40.000 --> 01:09:46.000
We need descriptions of each of the specific controls being proposed.

01:09:46.000 --> 01:09:55.000
We need to go through and actually identify the intent of each of those controls to address human activities.

01:09:55.000 --> 01:10:05.000
If we don't do that, then how do we know what that land use control is going to do to affect risk at the site.

01:10:05.000 --> 01:10:15.000
How does it prevent so it's basically how does it prevent or reduce exposure to hazards Then we need to go into who's actually going to be implementing those controls.

01:10:15.000 --> 01:10:27.000
And who's responsible for them? The part that we as an industry haven't really thought about in our records of decisions is operation and maintenance.

01:10:27.000 --> 01:10:50.000
If we have a record decision that includes more than just one-off construction activity surface or subsurface removal We need to be thinking through and including in that remedy how we're going to maintain the integrity of that remed going forward. So there was an example of

01:10:50.000 --> 01:11:08.000
Areas that you couldn't get into for whatever reason and you left TOI or MEC or whatever behind There's an operation and maintenance component of maintaining the integrity of that remedy If that remedy includes leaving things behind.

01:11:08.000 --> 01:11:26.000
And monitoring requirements. How are we going to monitor the activities at the site to make sure that we are protective.

01:11:26.000 --> 01:11:44.000
So this description of our selected remedy The goal there is to provide enough detail So that we can go into our design phase and complete our remedial action QAP and our land use control implementation plan.

01:11:44.000 --> 01:11:52.000
So that description is going to expand on those components from the evaluation of alternatives.

01:11:52.000 --> 01:12:04.000
For that selected remedy. To give that design engineer enough information to interpret the intent of the rod and have something that's implementable.

01:12:04.000 --> 01:12:12.000
And implementable means it's something that's contractable. So that the Army Corps can actually contract it.

01:12:12.000 --> 01:12:18.000
And that it can be physically implemented. If we can't figure out how to write a contract to do it.

01:12:18.000 --> 01:12:25.000
We're not going to be able to get to do it. And that's something we've learned the hard way a couple of times.

01:12:25.000 --> 01:12:28.000
We also need to make sure that we're not too specific.

01:12:28.000 --> 01:12:44.000
Because we have to anticipate that there are going to be some design changes and we need to be able to do those within the bounds of the selected remedy without having to go back and do some type of a broad modification.

01:12:44.000 --> 01:12:51.000
Cleanup levels are key. We need to document what those cleanup levels are.

01:12:51.000 --> 01:12:56.000
For munitions and what areas those levels are going to be applied to.

01:12:56.000 --> 01:13:06.000
What's the basis and rationale for those cleanup levels? Again, if our conceptual site model and our assumptions are off.

01:13:06.000 --> 01:13:17.000
Understanding the basis for those cleanup levels gives us an opportunity to be able to make some adjustments without necessarily having to go back and reopen our records of decision.

01:13:17.000 --> 01:13:24.000
And we need to be able to explain where and how those cleanup levels are going to be applied.

01:13:24.000 --> 01:13:28.000
How are we going to measure them? Where are we going to measure them?

01:13:28.000 --> 01:13:32.000
Those types of things. For land use controls.

01:13:32.000 --> 01:13:44.000
Explicit descriptions of those controls whenever possible. What's the intent of the control? What's the performance goal? What are we trying to accomplish with those land use controls?

01:13:44.000 --> 01:14:00.000
And how are we going to implement them? Putting just generic lists of land use controls in a record or decision and saying that Yeah, we're going to do this removal action and then we're just going to put these controls in place to manage residual risk.

01:14:00.000 --> 01:14:09.000
It's a good concept, but that's not implementable.

01:14:09.000 --> 01:14:17.000
So having gone through that kind of summary of a record of decision and the technical pieces of it.

01:14:17.000 --> 01:14:32.000
Now I'm going to get into more of what I find the interesting part and some real life lessons from real life lessons from some of my experiences in some of my experiences in Records of decision and how we've failed.

01:14:32.000 --> 01:14:40.000
Or how we've We've learned from our past mistakes, hopefully.

01:14:40.000 --> 01:14:47.000
Again, looking at the rod as a technical component as a technical document.

01:14:47.000 --> 01:14:53.000
Remedial action objectives. What do we need to make sure that's in our record or decision to be successful?

01:14:53.000 --> 01:14:59.000
What are we trying to do? Why are we doing it? Where are we doing it?

01:14:59.000 --> 01:15:05.000
How are we doing it? And what goal are we going to measure success with?

01:15:05.000 --> 01:15:11.000
That usually means cleanup levels. Those cleanup levels, as discussed earlier.

01:15:11.000 --> 01:15:30.000
Media specific. Okay, we're dealing with dirt unless we're underwater contaminant, munitions, what type of munition And levels, which generally means the depth We need to specify what we're going after.

01:15:30.000 --> 01:15:41.000
And that's That's a lot of times assumptions because we have very incomplete information on these sites from our RIs.

01:15:41.000 --> 01:16:00.000
Land use controls. This is the one that we should be able to control. This is the one we should have minimum uncertainty in implementing because pre-implementing the rod, we should be able to answer all of these questions about What controls, why do we need them?

01:16:00.000 --> 01:16:06.000
How are we going to implement them? Who's going to implement them is really critical sometimes.

01:16:06.000 --> 01:16:26.000
And what's the goal? We should be able to have the land use control components of our rod ready to go in in almost loose up form before that rod is signed so that when we do Turn the page, get the rod signed and start implementation.

01:16:26.000 --> 01:16:41.000
We're not having to step back and ask Okay, we need to do educational educational land use controls And at that point, finally start thinking about, well, who are we going to educate and what's our message?

01:16:41.000 --> 01:16:47.000
All of that stuff should be done in the feasibility study and should be clearly documented.

01:16:47.000 --> 01:16:59.000
In the rod. The other piece to keep in mind and never underestimate how badly it can send your project sideways.

01:16:59.000 --> 01:17:10.000
Is the summary information. All of that other important stuff about your site that's documented in the administrative record.

01:17:10.000 --> 01:17:21.000
You know, the terrain, is there accessibility concerns because it's a mountain or a swamp um Are there threatened and endangered species?

01:17:21.000 --> 01:17:33.000
Are there cultural resources? Those types of things. If those things haven't been really thought through and integrated into your your remedy selection process.

01:17:33.000 --> 01:17:39.000
You're going to have some challenges.

01:17:39.000 --> 01:17:56.000
So hopefully all of you recognize this table. It's step one of the DQO process from the remedial action QAP document in the COAP toolkit.

01:17:56.000 --> 01:18:05.000
A good test of are you do you think you're going the right direction with your record of decision is Can you fill out this table?

01:18:05.000 --> 01:18:22.000
While you're drafting your record or decision. Do you have the information you need to fill in not just for The CAPS focused on the MEC removal not just on the MEC removal part.

01:18:22.000 --> 01:18:34.000
But on the MEC treatment part and on the land use control parts, do you have enough information to know how you would implement it and how you would measure success.

01:18:34.000 --> 01:18:39.000
I have to say when we were putting this crop toolkit together.

01:18:39.000 --> 01:19:00.000
We searched for… probably a year trying to find a year trying examples of records of decision that we could use to say, hey, this is a good record decision and I couldn't find any. From my sites, I could not find one that had enough information to fill out this table.

01:19:00.000 --> 01:19:12.000
So that's a good challenge going forward. Can you do that? Because after that rod signed, you're going to have to fill out this table.

01:19:12.000 --> 01:19:19.000
So now a couple of interesting and unique.

01:19:19.000 --> 01:19:28.000
Lessons I've learned on things that you might not think are that important, but it They can be critical to the success of a project.

01:19:28.000 --> 01:19:38.000
The first one I've titled The Hopeless Cactus One. And you'll see why as I walk through this.

01:19:38.000 --> 01:19:43.000
No, that's not going to work.

01:19:43.000 --> 01:19:59.000
So a site, Delta Colorado, Western Slope. You can see from the picture rugged high mountain desert Home to the Uinta hookless cactus.

01:19:59.000 --> 01:20:18.000
It's a endangered species and this is critical habitat. And so in going through our RIFS, we identified the Endangered Species Act as an ARR and the hopeless cactus.

01:20:18.000 --> 01:20:32.000
There's a species of concern. We even went through our comparative analysis of alternatives and stated that And this was probably with some help from lawyers.

01:20:32.000 --> 01:20:44.000
That AR would be attained, including a discussion specifically of the cactus. And I'm not sure if you can read this on the screen, but it says.

01:20:44.000 --> 01:21:08.000
To comply with the regulation A current habitat survey for the Colorado hookless cactus would be reviewed and protection or relocation of the species could be required Before ground disturbing activities could begin.

01:21:08.000 --> 01:21:19.000
Anybody get a sense of the wouldas and couldas that are going to going to have a problem with it. They're going to make that statement a little bit of a challenge for us.

01:21:19.000 --> 01:21:29.000
What happened is what happened everybody read that and said, oh, okay, well, we've addressed, we've got a plan for addressing the cactus on the site.

01:21:29.000 --> 01:21:41.000
But when we went and actually wrote the selected remedy. We didn't include a component of the remedy for actually attaining that ARR.

01:21:41.000 --> 01:21:51.000
Well, what happened? Well, when you read that description. Somebody is going to magically do a habitat survey.

01:21:51.000 --> 01:22:04.000
And then… somebody else is going to review that and decide how to either protect or relocate that species before we can do any ground disturbing activity.

01:22:04.000 --> 01:22:14.000
Unfortunately. We didn't address any of that and we didn't put any of that into our contract for our contractor.

01:22:14.000 --> 01:22:32.000
And so a $50 million cleanup contract Never got in the field because we hadn't scoped doing the survey and coming up with a plan for how to address those cactus.

01:22:32.000 --> 01:22:45.000
This is where It's those little things that you think of, but if it's not written down in the record or decision it's probably not going to end up in the contract.

01:22:45.000 --> 01:22:54.000
And then you're going to have something out of scope that you may or may not be able to figure out how to address.

01:22:54.000 --> 01:23:04.000
Probably my most disappointing site. It's a beautiful cactus. But man has… Has it been a pain without a thorn?

01:23:04.000 --> 01:23:17.000
So the lesson learned from that. Document how your remedy is going to attain each ARR and describe that compliance as explicitly as possible in your rod.

01:23:17.000 --> 01:23:28.000
There's not going to be any magical information coming up between writing your record decision and doing your remedial design.

01:23:28.000 --> 01:23:37.000
That's going to add any more information. So make sure you've got all the information you need at the rod level.

01:23:37.000 --> 01:23:57.000
My… My next lesson learned is on… describing and addressing inaccessible areas and coming from colorado um That generally means steep slopes and mountains.

01:23:57.000 --> 01:24:09.000
And I've got a couple of examples of them. The lower picture is Camp George West artillery range on the west side of Denver, it's a mountain park.

01:24:09.000 --> 01:24:26.000
Probably about 800 feet of elevation with steep slopes. Most of The mountainside is a 20 to 30% slope. There are goalies coming through with steeper slopes and dense vegetation.

01:24:26.000 --> 01:24:37.000
The upper one is a small arms range where they decided to practice 40 millimeters In Northwest Colorado.

01:24:37.000 --> 01:24:51.000
And they were firing them into a very steep sloped mountainside as the backstop for the small arms range.

01:24:51.000 --> 01:25:04.000
So this is probably pretty common in terms of what a remedy will say that in inaccessible areas using AGC systems due to steep terrain.

01:25:04.000 --> 01:25:11.000
Other geophysics physical technologies will be utilized to the extent practical.

01:25:11.000 --> 01:25:24.000
And that makes sense. And that's great, except how do we define what inaccessible train is both for AGC and for analog?

01:25:24.000 --> 01:25:43.000
Do we go out and physically walk the site and determine from a field survey, what areas are accessible or not do we Do we have our GIS analysts come up with what they think is accessible or inaccessible?

01:25:43.000 --> 01:25:56.000
Most people don't work with terrain numbers, so When somebody walks up to you and says, hey, this is a 40% slope, I don't think it's accessible.

01:25:56.000 --> 01:26:12.000
Are people going to know what that is? Are they going to have a good feel for a 20% versus 30% or 40% slope and And is that something that's accessible with AGC or analog?

01:26:12.000 --> 01:26:28.000
Why do we care? Well, the uncertainty in delineating what those areas are can have a massive impact on your cost estimates and your risk of execution.

01:26:28.000 --> 01:26:43.000
In the case of Green Mountain, we've got 400 acres. And somewhere between 50 and 150 acres of that might be inaccessible.

01:26:43.000 --> 01:26:47.000
How do you contract for that? How do you put bids out for that?

01:26:47.000 --> 01:26:56.000
And if you haven't had those discussions prerecord a decision and have fidelity in how you're going to define those.

01:26:56.000 --> 01:27:13.000
How are you going to move forward with that? So don't underestimate the impacts of small things like defining accessible, inaccessible on your costs.

01:27:13.000 --> 01:27:18.000
The other lesson I learned was be very cautious of GIS slope analysis.

01:27:18.000 --> 01:27:30.000
In the case of the upper picture. They did a GIS slope analysis and they declared significant portions of that range.

01:27:30.000 --> 01:27:49.000
Inaccessible even for analog. The problem is that several of those inaccessible areas actually had the targets that these small arms range was using And they would go out each day to maintain their targets and walk right up into that inaccessible area.

01:27:49.000 --> 01:27:55.000
And adjust the targets and fire into the targets and all that.

01:27:55.000 --> 01:28:10.000
Make sure that you've had those conversations and you've well documented What's accessible, what's inaccessible, what the buffers around those are and And how that impacts your project.

01:28:10.000 --> 01:28:17.000
Finally, I'm going to talk about land use controls. We've learned a lot about these over the last few years.

01:28:17.000 --> 01:28:25.000
Generic descriptions of land use controls don't work.

01:28:25.000 --> 01:28:45.000
My project on Camp Hale in the East Fork Valley Our record of decision The component for land use control states remaining hazards at the site would be managed through educational land use controls, including U.S. Forest Service permit system.

01:28:45.000 --> 01:28:54.000
Warning signs, mech awareness training public communication and advisories on intrusive activities.

01:28:54.000 --> 01:29:02.000
That sounds great. But that's just a general list of things that are a good idea

01:29:02.000 --> 01:29:12.000
Nothing implementable and no details. U.s. Forest Service permits a lot of stuff.

01:29:12.000 --> 01:29:18.000
What are we expecting them to permit as part of this educational controls?

01:29:18.000 --> 01:29:24.000
Warning signs, warning whom about what, where are we going to place them?

01:29:24.000 --> 01:29:34.000
Mac awareness training. Who are we training? What are we training them about for MEC awareness?

01:29:34.000 --> 01:29:39.000
All of those types of things, if we don't know what those are.

01:29:39.000 --> 01:29:55.000
We can't implement them. We had to go back. As part of our developing our loose up And basically work through identifying all of the specifics of What were we trying to accomplish?

01:29:55.000 --> 01:30:06.000
Because our rod didn't have performance objectives. We didn't have any remedial action objectives or cleanup goals.

01:30:06.000 --> 01:30:11.000
Nothing measurable for For our land use controls.

01:30:11.000 --> 01:30:21.000
No strategies or intent of how to do it. No in-state, nothing to measure to be able to say whether we are successful or not.

01:30:21.000 --> 01:30:35.000
And I think that's something that's probably going to be in a lot of the records of decision that have been done that we're out there with now that we're just going to have to take a step back and really look at

01:30:35.000 --> 01:30:39.000
Okay, when we said that in the rod, what did we mean?

01:30:39.000 --> 01:30:44.000
Who are we trying to educate? What?

01:30:44.000 --> 01:30:54.000
What are we trying to achieve? What risk are we trying to reduce and how are we trying to reduce it?

01:30:54.000 --> 01:31:07.000
So my lesson learned from there is don't shortchange the land use controls component of your record decision. It's probably the hardest part to write. It's probably going to be the most detail.

01:31:07.000 --> 01:31:18.000
For each component of that of those land use controls. It needs to have equal detail and importance to any of the other components.

01:31:18.000 --> 01:31:25.000
When you look at that run document for each of those components of your land use controls.

01:31:25.000 --> 01:31:29.000
You should be able to answer. What's to control?

01:31:29.000 --> 01:31:34.000
Why do we have that control? How are we going to implement that control?

01:31:34.000 --> 01:31:41.000
Who's going to implement that control And with the WHO, do they actually know they're going to implement it and have they agreed to?

01:31:41.000 --> 01:31:49.000
And ultimately, what's the goal of that land use control? Before I get off land use controls.

01:31:49.000 --> 01:32:01.000
One other observation that I want to get out there If we're going to do surface-subsurface mech cleanup and land use controls.

01:32:01.000 --> 01:32:10.000
We like to go out and play in the dirt and we like to do the surface and subservice clean up part of it first and then think about land use controls.

01:32:10.000 --> 01:32:20.000
And I think we need to invert that. Land use controls are something that we can be implementing right away on all of these sites once those record decisions are signed.

01:32:20.000 --> 01:32:28.000
They're significantly the cheaper parts to implement, so we shouldn't be having budget constraints to getting those pieces out.

01:32:28.000 --> 01:32:37.000
So we should be First off, getting those land use control implementation plans in place and getting those controls in place.

01:32:37.000 --> 01:32:47.000
While we're working on the design and implementation of the MEC removal parts of our remedies.

01:32:47.000 --> 01:32:57.000
With that, um. Thank you all for listening to me. And if you have any questions.

01:32:57.000 --> 01:33:04.000
All right, Jeff, we got a couple of questions here, but we're running you ran a little over, but we'll get at least one or two of these in.

01:33:04.000 --> 01:33:13.000
Here's the first question. Can you give an example of cleanup level for a subservice mech removal.

01:33:13.000 --> 01:33:21.000
Yeah, so let's say i've got… Well, Camp George West.

01:33:21.000 --> 01:33:40.000
Our munition of interest is a 75 millimeter shrapnel or high explosive projectile and projectile our cleanup goal is subservice removal to 18 inches.

01:33:40.000 --> 01:33:50.000
Okay, next question. I've seen some rods that say land use controls that will be defined In the loose up.

01:33:50.000 --> 01:33:59.000
Is that something that is specific action oriented enough to include in the rod or would you not recommend that?

01:33:59.000 --> 01:34:05.000
That is a perfect example of the worst case scenario for a recorder decision.

01:34:05.000 --> 01:34:19.000
Because you haven't decided what components, what land use control components are your remedies. So how can you judge your remedy as being protective.

01:34:19.000 --> 01:34:24.000
When you sign it, if you don't know if you sign it if you don't know if what controls are going to be in place.

01:34:24.000 --> 01:34:30.000
That's really setting yourself up for two records of decision.

01:34:30.000 --> 01:34:37.000
All right. This is really refreshing to hear. It keeps moving on me. Here we go.

01:34:37.000 --> 01:34:47.000
It's really refreshing to hear real examples of what could have been better Is this documented in a best management practices guide somewhere?

01:34:47.000 --> 01:34:51.000
No. Not that I'm aware of.

01:34:51.000 --> 01:35:13.000
All right. Got time for one more question. A big issue with accountability versus inaccessibility in describing to what or whom an area is inaccessible and why An area can be inaccessible to a towed AGC sensor but accessible to handheld instruments

01:35:13.000 --> 01:35:20.000
And recreational receptors. Descriptions often leave this out and just describe inaccessible areas.

01:35:20.000 --> 01:35:25.000
Which is inadequate for our purpose. Would you agree?

01:35:25.000 --> 01:35:39.000
Yeah, and hopefully, I mean, that was part of my point is that not only Do you need to acknowledge that there are going to be areas that are not accessible to to these AGC systems.

01:35:39.000 --> 01:35:50.000
But you also have to acknowledge that there's going to be you that if you have uncertainty in how big those areas are, that's going to be a challenge as well.

01:35:50.000 --> 01:35:56.000
But yeah, you need to say How are we going to deal with inaccessible areas?

01:35:56.000 --> 01:36:06.000
And how are we going to deal with areas that are not not safely accessible for a UXO tech with a Seanstadt.

01:36:06.000 --> 01:36:11.000
Because you're going to run into those areas as well.

01:36:11.000 --> 01:36:16.000
All right. That was the last question. Thanks, Jeff. I really appreciate it. We need to keep pressing on.

01:36:16.000 --> 01:36:17.000
Sorry for my lack of time management.

01:36:17.000 --> 01:36:26.000
That's all right. All right, we have our last, fourth, and last presentation.

01:36:26.000 --> 01:36:42.000
Lise Goggin, and she will be presenting RA Lessons Learned. And remember, any questions you put up here we will They will be sending us the presenters a copy of these questions so they could possibly answer them Offline.

01:36:42.000 --> 01:36:44.000
Lise, it's on to you.

01:36:44.000 --> 01:36:47.000
All right. Can y'all see my screen?

01:36:47.000 --> 01:36:49.000
Yes, we can.

01:36:49.000 --> 01:37:00.000
Great. All right. Well, I liked one of those questions because it talked about lessons learned and how to apply those, which is one of the focuses of this presentation.

01:37:00.000 --> 01:37:09.000
I think I'll be touching on a lot of the same issues that some of the previous presenters brought up, but we're going to look at maybe how to address those.

01:37:09.000 --> 01:37:15.000
By applying those lessons learned.

01:37:15.000 --> 01:37:32.000
All right, so what's the point of this presentation? I think probably a lot of folks on the line are aware that at USACE we had a goal too, and this was to get actually the current goal two is to get 100 projects to response complete by 2030.

01:37:32.000 --> 01:37:38.000
So we've been in the process of trying to reach that goal now for a couple of years.

01:37:38.000 --> 01:37:50.000
And we've hit some speed bumps along the way. I'd like to think that some of those speed bumps were little, but I think some of them looked like the one in the picture here. So we've hit some pretty big problems. We've heard about a few of those.

01:37:50.000 --> 01:37:55.000
So this presentation, we're going to kind of look at those and see what we've learned to help us meet.

01:37:55.000 --> 01:38:05.000
Our goal. So I'm going to focus on four general areas of speed bumps as we're going to call them in this presentation.

01:38:05.000 --> 01:38:18.000
First, projects that are extremely large areas requiring MEC removal. Camp Fannin would be one of those examples. I think DJ gave a really good summary of that project in particular.

01:38:18.000 --> 01:38:38.000
We'll also look at site-specific challenges. I think I think Jeff did a good job of talking about how we need to be site specific when we're riding our rods. And so we'll look at how that has impacted us on our projects. We'll also discuss holes in the CSM. Maybe when we had an older RI and we

01:38:38.000 --> 01:38:46.000
We didn't gather enough data to completely fill out that CSM. How has that impacted us? And then underestimating rod language, I think.

01:38:46.000 --> 01:38:54.000
Several of the previous presentations focused on the importance of rod language so We'll look at that again.

01:38:54.000 --> 01:39:15.000
And so, as I said, I think What we want to do here is think about how to apply these lessons learned. This is kind of the step in the quality process that often gets overlooked. A lot of times we'll document lessons learned. We'll talk about them, but then we often or sometimes fail to actually apply a fix.

01:39:15.000 --> 01:39:29.000
To prevent those lessons from reoccurring. And then lastly, we'll talk about what to do if we already have a rod in place. I think a lot of these lessons learned, we're going to be looking backwards at what could we do in earlier phases of the circular process.

01:39:29.000 --> 01:39:33.000
But we'll also address what we could do we already have those rods in place.

01:39:33.000 --> 01:39:53.000
So bump number one, this is where we're talking about those large MEC removals. Sometimes we refer to these sites as elephants or eating an elephant is another presentation that was given at the stand down if anyone was lucky enough to see that one given by Julie Birdie. So I've latched on to the elephant theme here.

01:39:53.000 --> 01:39:59.000
So just an example here, we've got a site where the selected remedy is surface and subsurface removals.

01:39:59.000 --> 01:40:11.000
With land use controls, lots of detail there. Just kidding, but that's just a summary, but we would want to see more detail in that. Unfortunately, some of our older rods we know don't have much more detail than that.

01:40:11.000 --> 01:40:18.000
So this site is over a thousand acres. The cost of the remedial action is going to be over 50 million.

01:40:18.000 --> 01:40:23.000
And all we really know about the land use is that we have recreation and forestry at this site.

01:40:23.000 --> 01:40:38.000
So we've got a huge site. We've got a cost prohibitive remedy And we have broad and generic land use. These are problems, right? And they're problems that we have on a lot of our sites where we did in our eye quite a long time ago.

01:40:38.000 --> 01:40:52.000
Where maybe we weren't focused on some of these details as much. So what we've basically done is we've taken this elephant And we've painted it red, right? So we know elephants can be dangerous, right? We know they could um

01:40:52.000 --> 01:41:04.000
Could hurt us if we got caught in a stampede. So we've painted that elephant red completely because we're like, that elephant is dangerous but I think if we were to think about this elephant in a little bit more detail.

01:41:04.000 --> 01:41:25.000
We could kind of say, well, you know, when I look at that tail, I don't think that's that dangerous. We could call that pretty safe. And maybe those big floppy ears wouldn't hurt us and Maybe that trunk is really just a big water gun, right? So, you know, when I think about it, really the only things I'm kind of worried about with this guy is like the feet stomping on me or the tusks

01:41:25.000 --> 01:41:40.000
Impaling me, right? So maybe the rest of them is just kind of like this medium, medium risk. So we've now taken that elephant. We've really divided it up into different levels of risk, right? We've looked at what what could hurt us the most, what could hurt us the least.

01:41:40.000 --> 01:41:51.000
And that's the idea that we want to start to look at when we're doing our RI is kind of evaluating where we might have different levels of risk.

01:41:51.000 --> 01:42:06.000
So applying this lessons learned, right? We're going to go back to the RI. So on future projects, when we're completing an RI, this is something we want to focus on so that we prevent ending up we prevent ourselves from ending up in the same situation we have been.

01:42:06.000 --> 01:42:21.000
On some of these existing RAs. So I've got a little diagram here. It's a James Salisbury original. I've got Memojis collected for him that I can use in presentations since I often find myself quoting him.

01:42:21.000 --> 01:42:29.000
You can see here, we're really in the RI, we want to focus on both where we have MEC, which we often do a pretty good job of that.

01:42:29.000 --> 01:42:39.000
In today's world. But a lot of times we don't do as good of a job as looking at the site specific risk. Where do we have specific receptor activities?

01:42:39.000 --> 01:42:57.000
Where are people using that site? And both of those elements, the presence of MEC and the types of activities and how often people are using that site impact our risk. So this is something that geophysicists, we like to focus on where's the mech. We collect the data.

01:42:57.000 --> 01:43:12.000
To tell us where that mech is, but I will definitely admit that I think the uh the receptor activities and the land use getting very good detailed land use data is probably more important than geophysics on a lot of sites.

01:43:12.000 --> 01:43:29.000
We'll at least say equally important. So bottom line, what we want to do when we're going through our RI and working into our FS is to develop remedial alternatives that address site-specific risk scenarios rather than applying one remedial process to the entire site.

01:43:29.000 --> 01:43:46.000
So rather than painting that elephant red, let's think about what parts of that elephant we might be able to paint green and yellow. And I think that's going to give us the ability to make better decisions and get us to more realistic, more protective And site-specific remedies.

01:43:46.000 --> 01:43:53.000
All right, bump number two, site-specific challenges. We, you know, I think DJ talked about a lot of challenges that he ran into.

01:43:53.000 --> 01:44:02.000
At Camp Fannin. And this is an imaginary site, but I've made up an example here where once again, we have a selected remedy.

01:44:02.000 --> 01:44:08.000
Agc survey and subsurface removal. Over 100% of the 100 acre site.

01:44:08.000 --> 01:44:34.000
Unfortunately, at this site, we also have endangered squirrel dens. So this is similar to potentially Jeff's cactus. So we have endangered squirrel dens located throughout the site. We cannot disturb these. There are cattle ponds scattered throughout the site. Dj talked about ponds in his presentation. These are real things that we're running into on a lot of our projects, right? We have fencing. So all these red lines on this map are fences that the landowner

01:44:34.000 --> 01:44:54.000
Doesn't want removed, but also fence repair is a primary subsurface receptor activity. So we got to think about how we're going to protect those those folks that are actually repairing that fence, pounding in new posts if we're not able to remove the fence and properly detect and remove any mech that may be present underneath them.

01:44:54.000 --> 01:45:06.000
And then additionally, there are steep ravines throughout the site. Okay, so now it's time for you all to participate. So we complete this RA, but we only cover 80% of the site with AGC and removal.

01:45:06.000 --> 01:45:09.000
Can we claim response complete?

01:45:09.000 --> 01:45:21.000
All right, I'm about to launch a poll, ladies and gentlemen. A new box is going to pop up on your screens, which will allow you to answer this question. Can we claim response complete? It's either a yes or no.

01:45:21.000 --> 01:45:27.000
Click the circle to the left of the answer that you think is right and then hit that blue submit button in the lower corner.

01:45:27.000 --> 01:45:33.000
It looks like about 20% of you have responded, but those answers are coming in quick and fiercely.

01:45:33.000 --> 01:45:41.000
We do have some agreement, but there is a little bit of a variation. So we might need to talk the audience through what the right answer is.

01:45:41.000 --> 01:45:49.000
So I'll give you all just a few more seconds to think it over and submit your response and we'll close this one out in three.

01:45:49.000 --> 01:46:00.000
Two, one. Let's take a look at those results. So about 90% said, no, we can't complain response complete. But about 10% thought we could.

01:46:00.000 --> 01:46:02.000
Elise, what's the answer?

01:46:02.000 --> 01:46:14.000
All right. Thanks, Dean. Yeah, the answer is no. So 90% of you guys were correct here. So we have not completed the remedy over 100% of the site.

01:46:14.000 --> 01:46:28.000
So at this point, without doing additional action of some sort, we cannot claim response complete. I'd be interested to hear thoughts or questions about maybe from some of those folks that said, yes, we could complete it.

01:46:28.000 --> 01:46:40.000
But kind of moving into the lessons learned portion of this bump, right? So this is again, how are we going to apply lessons learned to prevent this sort of thing from happening again?

01:46:40.000 --> 01:46:51.000
Where perhaps we don't cover 100% of the site. So I think, again, it goes back to that doing an RI, thinking about these things in a bit more detail.

01:46:51.000 --> 01:47:10.000
What are our site-specific challenges? I think Jeff talked about some of the accessibility issues, right? Where can different types of sensors Where can they be deployed? So thinking about that. In order to think about that during an RI, what we're going to need to do is start with principal study questions, right? So in our quack

01:47:10.000 --> 01:47:15.000
That's the place where we're writing up those principal study questions in our DQOs.

01:47:15.000 --> 01:47:23.000
That are going to make sure that we answer the right questions to be able to design proper remedial alternatives if necessary.

01:47:23.000 --> 01:47:37.000
So what areas are inaccessible to receptors? That's something that didn't really come up here, but we have different types of inaccessibility. Are they inaccessible to the DGM sensors of various types?

01:47:37.000 --> 01:47:43.000
And configurations, are they accessible to receptors? Where do we have biological or cultural restrictions? All of those things.

01:47:43.000 --> 01:47:52.000
If we incorporate those as principal study questions, we should be able to get ourselves in better shape moving into the FS.

01:47:52.000 --> 01:47:58.000
Again, focusing on the DQOs, developing decision rules related to assessing risk within bodies of water.

01:47:58.000 --> 01:48:05.000
This is often something that has been overlooked in the past. We might have a creek or we might have a pond.

01:48:05.000 --> 01:48:10.000
Did we look at whether there is unacceptable risk in that body of water or not?

01:48:10.000 --> 01:48:25.000
We can't simply, especially if our rod doesn't address that we can't just simply ignore that pond, right? We have to say why we're being protective of any receptors that might use that body of water. So let's focus on gathering that data in the RI.

01:48:25.000 --> 01:48:39.000
Develop site-specific alternatives during the FS. Again, all of this RI data is going to allow us to develop those site-specific alternatives. So you might also have to get protective or get creative in order to be protective. Sorry about that.

01:48:39.000 --> 01:48:47.000
You know, with the squirrels, that's a tough one, especially if they move around and create new dens all the time.

01:48:47.000 --> 01:48:54.000
Things of that nature. You might need to identify and monitor squirrel dens during remediation to ensure maximum coverage is obtained.

01:48:54.000 --> 01:49:05.000
Place signs to warn receptors of remaining hazards at squirrel den locations that were not remediated. Things like this, right? We might have to think outside of the box of the standard five remedial alternatives that we used to see.

01:49:05.000 --> 01:49:15.000
And make sure that we're covering all of our bases with specific remedies or remedial alternatives to address site specific risk.

01:49:15.000 --> 01:49:29.000
And then increase effective communication with stakeholders. For instance, if we can't get a landowner to remove a fence, how did we ask them to remove the fence? Did we explain why it's in their best interest to remove the fence?

01:49:29.000 --> 01:49:39.000
Did we explain would be replacing the fence? Also gathering information from our stakeholders, right? Asking them questions to make sure we're fully informed.

01:49:39.000 --> 01:49:48.000
As we work through this process together. All of these things ideally would help us address those site-specific challenges.

01:49:48.000 --> 01:50:06.000
Better once we get to that remedial action phase. Bump number three, holes in the CSM. And again, I think this is something that we probably will always encounter. It's near impossible to get a complete CSM, I think, during the RIFS phase.

01:50:06.000 --> 01:50:12.000
So I think this is something that we just need to focus on minimizing the holes in the CSM.

01:50:12.000 --> 01:50:21.000
A few examples here. Extent has not been determined. So the MRS boundary is wrong. I've seen this on numerous occasions. And what does this lead to in the RA?

01:50:21.000 --> 01:50:30.000
Typically, never-ending step outs and or a discussion about how to handle the contamination that might be outside of our boundary.

01:50:30.000 --> 01:50:44.000
Vertical profile is incomplete or based on the wrong data. I've often seen where we've correlated the depth of MD to the depth of MEC, which we know which we know is not typically the correct way to do that.

01:50:44.000 --> 01:50:49.000
So where do we end up in our RA? We end up with a change in CSM identified during the RA.

01:50:49.000 --> 01:51:00.000
That requires a rod amendment to be protective. We've seen this multiple times. And then anomaly densities are much higher than anticipated. This is one we're probably all used to seeing.

01:51:00.000 --> 01:51:12.000
And specifically related to technology evolution. But if, for instance, at a site we don't anticipate really high anomaly densities, we probably aren't going to plan for anomaly reduction.

01:51:12.000 --> 01:51:19.000
So we won't have sufficient funding and we won't be able to effectively complete that remedial action.

01:51:19.000 --> 01:51:29.000
So applying lessons learned from situations like this where we have holes in our CSM, again, we're going back to that RI, right? We're looking at the RI task orders.

01:51:29.000 --> 01:51:38.000
And making sure that they're flexible. This is one thing that I know has been a frustration for both the government and the industry side for a while.

01:51:38.000 --> 01:51:48.000
Is that trying to complete an RI just under one firm fixed price task that says complete RI typically is not going to get us all the answers we need.

01:51:48.000 --> 01:51:53.000
Because there are too many unknowns. So using options, using phased approaches.

01:51:53.000 --> 01:52:02.000
Things of that nature, contractual tools of that nature, I think can help us get more information and get a more complete CSM.

01:52:02.000 --> 01:52:18.000
And then related to the vertical profile, EM 200-1-12 does discuss the vertical distribution. And it does state that MD alone is not a reliable predictor of MEC depth.

01:52:18.000 --> 01:52:27.000
So we need to keep that in mind. Let's use RA data from similar sites. Certip ESTCP models as available.

01:52:27.000 --> 01:52:36.000
Professional judgment and experience. I think we have a lot of folks who know how these ranges are used. We know a lot about how these munitions were fired.

01:52:36.000 --> 01:52:49.000
That combined with kind of our geology and our local terrain, I think can help us give really give a good basis for our estimate of how deep we expect things to go.

01:52:49.000 --> 01:53:01.000
And then consider performing a remedial design if we still have CSM data gaps after the RI. I think we've done a lot better with this in recent years, but it's something to still consider.

01:53:01.000 --> 01:53:18.000
If we feel like we don't have all of the data we need to be successful moving into the RA, Let's do a remedial design, gather more data to help support the completion of the RA. We like to rush through this a lot.

01:53:18.000 --> 01:53:33.000
And maybe skip this step because we're intent on meeting those goals. But I think we've seen time and again that when we do skip this, when there's a reason to go go forward with a remedial design, we end up having challenges in completing our RA.

01:53:33.000 --> 01:53:44.000
So, and then focus on completing a detailed vertical profile during the RI. I think I think both Nancy and Jeff touched on the RAO a bit.

01:53:44.000 --> 01:53:51.000
And this is really the backbone of your RAO, understanding how deep your contamination is, where your contamination is.

01:53:51.000 --> 01:53:56.000
And then where your receptor activities are and how deep they go.

01:53:56.000 --> 01:54:11.000
That alone is going to help you get to better and more protective or not more protective, but protectiveness is a binary, but we'll help you get to protective remedial alternatives.

01:54:11.000 --> 01:54:18.000
Underestimating rod language. This is one that we still see pretty regularly.

01:54:18.000 --> 01:54:25.000
When we look at rod language, I think oftentimes we don't take it very literally.

01:54:25.000 --> 01:54:37.000
And that's often what gets us into trouble. Got a few examples here and we're going to ask for more crowd participation. Trying to wake you guys up at the end of this long.

01:54:37.000 --> 01:54:49.000
This long teleconference The selected remedy is subsurface removal using AGC, but the contractor proposed digging and sifting part of the site. Should USACE award the task order to this contractor.

01:54:49.000 --> 01:54:53.000
All right, we have launched another pop-up poll with that question.

01:54:53.000 --> 01:55:08.000
So let's go ahead and select yes, no, or it depends. Click the circle to the left of one of those answers and then hit the submit button. If for any reason you're having technical difficulties with the poll, you can always type an answer into the Q&A. We will count that towards your participation.

01:55:08.000 --> 01:55:23.000
So it looks like about a third of you have responded. I'll give you just a few more seconds here to cast your vote. And quickly, if you're with a group doing a viewing party, I know there's two groups out there watching. Please fight it out amongst yourselves and cast a representative vote for your team.

01:55:23.000 --> 01:55:27.000
All right, let's go ahead. I'm seeing some no's come into the chat.

01:55:27.000 --> 01:55:40.000
I'm going to close this poll here in three, two, one. All right, Elise, it looks like About 70% of them are saying it depends, although almost a quarter said no.

01:55:40.000 --> 01:55:48.000
Yeah. All right. Interesting answers. And I do like the it depends answer because it's a good one to always fall back on, right?

01:55:48.000 --> 01:56:11.000
Talk to Office of Counsel, talk to your KO. Those are definitely um good valid reasons for going with that answer. In this case, I think it was pretty clear and I guess I did make some assumptions, but no, we don't want to select a proposal that includes, I guess, tasks that aren't

01:56:11.000 --> 01:56:16.000
Going to get us to response complete, right? Dig and sift is not the selected remedy in this case.

01:56:16.000 --> 01:56:24.000
If we go ahead and award that proposal when we said we are awarding a task order to get us to response complete.

01:56:24.000 --> 01:56:38.000
We're not going to get there in most cases. So I can see that it depends answer. So I'm going to give that one to you guys too. But let's go to the next one. So the rod says the remedy is applied to the whole site, but during a site visit, we see a pile of old cars.

01:56:38.000 --> 01:56:45.000
So we determined that is an exception area and we do not apply the remedy to that area. Can we get to RC if we exclude this area?

01:56:45.000 --> 01:56:52.000
All right, I've launched a poll again and you'll have those choices of yes, no, it depends. Go ahead and click the circles.

01:56:52.000 --> 01:56:57.000
It looks like they're getting the hang of it. Those answers are coming in pretty quickly here, ladies and gentlemen.

01:56:57.000 --> 01:57:03.000
Let's see, can we get to response complete if we exclude this area? Pardon me.

01:57:03.000 --> 01:57:07.000
A couple of people are chiming into the Q&A saying yes.

01:57:07.000 --> 01:57:14.000
And I'm seeing some commentary about why they're picking that. But I'll go ahead and give you just a second here to submit your vote.

01:57:14.000 --> 01:57:28.000
And then let me close it down here in three two One. All right. And at least in this case, about 75% of them said no. And it was almost an even split between yes and it depends.

01:57:28.000 --> 01:57:49.000
Wow, this is so interesting. I'm loving this. So I channeled the first round on this answer. So I said it depends right so We can if we determine the remedy would still be protective and we follow the process to change the rod. And that's something I'll talk about in a few slides here is changing the rod.

01:57:49.000 --> 01:57:58.000
So, you know, I can understand the no's as well because without going through that process, then we wouldn't be able to.

01:57:58.000 --> 01:58:02.000
So let's see if we can all get on the same page on one more.

01:58:02.000 --> 01:58:10.000
The rod doesn't mention analog methods, but there are areas that are challenging to map with DGM sensors. So we use analog methods to clear those areas.

01:58:10.000 --> 01:58:13.000
Can we claim response complete?

01:58:13.000 --> 01:58:18.000
All right, ladies and gentlemen, our third and final question has been popped up in that new window.

01:58:18.000 --> 01:58:23.000
It's a yes, no, or it depends. Go ahead and click the circle to the left and cast your vote.

01:58:23.000 --> 01:58:30.000
They are jumping on in and it's quite a battle. The answers are bouncing around.

01:58:30.000 --> 01:58:36.000
Again, if any technical difficulties here, you are certainly welcome to type them into the Q&A as an individual response.

01:58:36.000 --> 01:58:43.000
And we are having some commentary on why people might answer the way they are and some questions. I've got some no's that have come in there.

01:58:43.000 --> 01:58:51.000
I'm going to go ahead and close this one with two thirds of the audience having to vote. Let me close it down here in three.

01:58:51.000 --> 01:59:00.000
Two, one. And sadly, I would say we have not gotten towards consensus. We have all been even split here.

01:59:00.000 --> 01:59:06.000
With no, just a little bit further in the lead, no taking about 40% of the votes, Elise.

01:59:06.000 --> 01:59:20.000
All right. I like this. I think this is great. This is a great way to see kind of why some of these things are are presenting challenges for us. So I appreciate everyone who's participating in this.

01:59:20.000 --> 01:59:28.000
Yeah, so in this case, I said, no, we did not implement the selected remedy or follow DoD policy.

01:59:28.000 --> 01:59:42.000
So I think it was um Nancy earlier who referred to the DoD policy to maximize the use of DGM. And then, of course, FUD's policy to maximize the use of AGC.

01:59:42.000 --> 01:59:51.000
I definitely would be interested to hear more about the people who answered differently than me because we all know I'm not always right.

01:59:51.000 --> 01:59:56.000
Yeah, definitely would like to follow up with folks after this.

01:59:56.000 --> 02:00:22.000
But anyway, just kind of bringing the uh this bump to the lessons learned phase Really, it's as simple as following the yellow brick rod which big fan here. So I like to put in a musical image in every presentation. But really, the lesson learned here is complete the selected remedy as defined in the rod

02:00:22.000 --> 02:00:32.000
Or follow the designated process to change the rod. Those are really our two options once we have a rod in place.

02:00:32.000 --> 02:00:41.000
So just to kind of summarize those bumps, success in the RA phase depends on a well-characterized site and site-specific remedial alternatives.

02:00:41.000 --> 02:00:55.000
So again, a lot of those lessons learned, we need to start to apply those in the RI phase and the FS phase in order to ensure that we're not having these problems hit us again in the future.

02:00:55.000 --> 02:01:06.000
So I know I'm probably coming up here close on time. The polls have extended my time a little bit, so I'm going to move quickly through some of these because there's a lot of text on these slides.

02:01:06.000 --> 02:01:20.000
But one thing to keep in mind is that what we write in the FS is ultimately going to end up in our rod, right? So one of those remedial alternatives is going to be the selected remedy.

02:01:20.000 --> 02:01:28.000
And then we are going to the lead agency is going to have to implement that as described. So thinking about that at the FS phase, I think is super important.

02:01:28.000 --> 02:01:35.000
And will help us get to the successful implementation of the remedy down the road.

02:01:35.000 --> 02:01:41.000
So example language, again, this is all just examples, not guidance, not direction.

02:01:41.000 --> 02:01:49.000
But, you know, just kind of giving you guys an idea. So again, I'm not going to read through all of these. I've provided the text in the slides.

02:01:49.000 --> 02:02:08.000
So that y'all can have them to reference but We do need to acknowledge areas where we can't reasonably perform treatment while explaining while it's still while it is still protective. So I've given an example here. You know, we're explaining why we think it is still protective because it's a very insignificant percentage of the site.

02:02:08.000 --> 02:02:21.000
We're stating where MEC may remain under trees In the, where did I say in the creek in the bottom of the creek. But we've also stated there's no anticipated receptor activities in the creek.

02:02:21.000 --> 02:02:31.000
So we're not only stating where we can't perform treatment. We're stating why we still think this alternative is protective and that's the important part.

02:02:31.000 --> 02:02:39.000
Use language that allows for the use of different technologies while stating the preference for AGC. Again, this is what we've talked about over and over again.

02:02:39.000 --> 02:02:45.000
You know, it is fine to give ourselves flexibility. I think Jeff mentioned that in his presentation.

02:02:45.000 --> 02:03:01.000
Where we may understand that we haven't walked 100% of this site. So there might be different types of terrain or features that we haven't predicted. So giving yourself a little bit of flexibility But also making sure that we have an approval process in place

02:03:01.000 --> 02:03:13.000
For demoting our technology from AGC to non-AGC DGM to analog. And then explaining the anticipated depth of the detection for different sensors.

02:03:13.000 --> 02:03:24.000
You know, especially with older RIs, we're probably looking at detection with an EM61, which has a different depth of detection than a lot of our newer AGC sensors.

02:03:24.000 --> 02:03:42.000
So making sure that we're understanding both what we detected in the RI And what we would likely detect in the in the RA and making sure that correlates with our vertical profile The last little bit in blue there, all detected TOI will be investigated regardless of death, depth.

02:03:42.000 --> 02:03:57.000
This is definitely a recommendation unless there's a cost prohibitive or some other thing that, you know, a PDT needs to consider for why we wouldn't want to remove TOI that we detected.

02:03:57.000 --> 02:04:12.000
Example related to features that interfere with detection capabilities. Again, this kind of comes into Power lines, we have agency data collected underneath power lines where we had 100% success with AGC classification.

02:04:12.000 --> 02:04:26.000
So we don't want to see these just automatically go to analog, but we do need to consider them and make sure we've thought about how that might impact the implementation of the remedy. Fencing we talked about briefly.

02:04:26.000 --> 02:04:37.000
If we do get agreement, and I think this was sort of asked to Nancy earlier, how do we document agreement with some of our stakeholders?

02:04:37.000 --> 02:04:42.000
Again, I think she said talk to OC, which is a very wise answer that we should always do.

02:04:42.000 --> 02:04:47.000
But an MOU or an MOA also can show that we've reached an agreement.

02:04:47.000 --> 02:04:54.000
In this case to remove fencing. So we can look to do that as well. Example of a site-specific constraint.

02:04:54.000 --> 02:05:12.000
Got natural gas line. So I've definitely seen sites where there's utilities that have restrictions So we want to think of other ways to mitigate the unacceptable risk in this area. In this case, this example, providing coordinates of any targets of interest to the Forest Service in that area.

02:05:12.000 --> 02:05:18.000
And educating them on what that means could be something we consider.

02:05:18.000 --> 02:05:31.000
So… Enough with the rod language. And I've touched on this a bit but I think a lot of times we seem like we're afraid to change a rod that's already been written.

02:05:31.000 --> 02:05:38.000
And the reason there is a process for changing is because we anticipate that we might need to change our decision, right?

02:05:38.000 --> 02:05:50.000
And so we don't want to think of it as a bad thing. We want to think of it as something we need to do in order to be protective in order to address changes in conditions at the site.

02:05:50.000 --> 02:05:58.000
So if you need to make a change, we want to talk to office counsel. We might need to do something in MFR, ESD, Rod amendment.

02:05:58.000 --> 02:06:04.000
And they'll be able to help guide us on what would be appropriate.

02:06:04.000 --> 02:06:10.000
And other things we can do would be to consider delineation to optimize the implementation of the remedy.

02:06:10.000 --> 02:06:18.000
Especially on a very large site, if we know there are areas that we definitely want to get that removal done quickly.

02:06:18.000 --> 02:06:27.000
It might be in our best interest to delineate those areas out. And maybe we've considered, oh, we could do a different, we might need to change the remedy.

02:06:27.000 --> 02:06:44.000
For instance, in a different part of the site, delineation will help us do that more efficiently. And then complete remedial design. We touched on that, but I think that can often be a solution that can get us a lower risk RA, I guess.

02:06:44.000 --> 02:07:01.000
So in summary, I think we've learned you'll only remember 7% of what I said today. So here's the five bullets that I think we should remember we want to use the RI to characterize accessibility, both of receptors, sensors, any other field activities.

02:07:01.000 --> 02:07:07.000
Collect detailed land use data in the RI. Where are we seeing specific receptor activities performed?

02:07:07.000 --> 02:07:17.000
Throughout the site. Don't paint the entire elephant red. Different parts of the site likely have different risk scenarios that can be mitigated using different response actions.

02:07:17.000 --> 02:07:23.000
Write specific remedial alternatives and explain how they are protective over the entire site.

02:07:23.000 --> 02:07:37.000
Here's a typo. And then take the rod language seriously. What we write in there, we need to be implementing or we need to be changing through the process. And that's that last bullet. Use that established process to change the rod when needed.

02:07:37.000 --> 02:07:40.000
And with that, I think I am done. So any questions?

02:07:40.000 --> 02:07:46.000
All right. Great job, Elise. Yeah, we've got three questions here. We're not going to have time to get through them all.

02:07:46.000 --> 02:07:56.000
So let's see here. Oh my gosh, actually got four more here. All right, I'll just start with the oldest one. Can the rod say 100% of an area except steep ravines?

02:07:56.000 --> 02:08:15.000
If so, does the exact acreage and location of the steep ravines need to be accurately defined in the rod Is there wiggle room if… inaccessible areas are found to be larger or smaller than the estimate than estimated in the rod.

02:08:15.000 --> 02:08:31.000
Okay, so I would answer this by asking the person who asked the question, accessible to what? Do we have unacceptable risk in the ravines? How are you mitigating the unacceptable risk in the ravines?

02:08:31.000 --> 02:08:37.000
Again, this isn't an easy question to answer directly because I don't have all of the information.

02:08:37.000 --> 02:08:49.000
And that's really what we need to start thinking about during that RI. If you have an area with steep ravines, figure out what the risk scenario is in those ravines.

02:08:49.000 --> 02:09:01.000
And then address that through the process. So that's not probably the answer you were looking for, but that's that's really the process that we're trying to get folks thinking about.

02:09:01.000 --> 02:09:20.000
Okay, I got one last one here. For the areas that are too difficult to access for AGC, Why have I been told CX would rather have no data than digital or analog handheld magnetrometers during the RI, why are we taking a great tool away?

02:09:20.000 --> 02:09:28.000
I don't know. It's not up to the CX, right? It's up to what's written in your rod.

02:09:28.000 --> 02:09:37.000
I would say that I don't think the CX takes that position. The CX, we have policy that we follow, whether that's FUDs or DOD.

02:09:37.000 --> 02:09:50.000
Or maximizing DGM and AGC. And it's all about, again, characterizing that risk in the ri And then making sure that that risk is addressed.

02:09:50.000 --> 02:09:56.000
And any unacceptable risk is mitigated through the remedial alternative that we end up selecting.

02:09:56.000 --> 02:10:04.000
Again, probably a non-answer, not the answer you were looking for but That's the process we're working with.

02:10:04.000 --> 02:10:09.000
All right. Thanks, Elise. I'd like to real quickly thank Elise, Jeff.

02:10:09.000 --> 02:10:15.000
Dj and Nancy for putting on And presenting some really, really good presentations. Had a lot of good questions on them.

02:10:15.000 --> 02:10:34.000
Remember that we're going to try to put at least one more webinar this year. Again, more presentations from the stand down Hopefully we can maybe get something out in June or July, probably July. But again, I will send out an email to everybody that hopefully you've been getting them there or watching the Clue Inn website.

02:10:34.000 --> 02:10:41.000
For this coming up. Other than that, I'd like to thank you all for coming. And I'm going to turn it back over to Gene to finish everything up.

02:10:41.000 --> 02:10:51.000
All right. Thank you so very much, Jeff. I want to echo your thanks to all of the speakers and panelists who joined us today, as well as you, Jeff, for taking time to help organize these talks and bring them to the Cluwin audience.

02:10:51.000 --> 02:11:06.000
Let me walk through just a few quick final reminders. I encourage you to visit us at cluwen.org and make sure you sign up for our free monthly newsletter, Tech Direct, if you're not already subscribing. I will announce free technical transfer events like today's session in that newsletter that I send out on the first of each month.

02:11:06.000 --> 02:11:25.000
Now, if you weren't there at the beginning, I'll just remind everybody there is a seminar homepage where we have already posted the presentation materials from our speakers, along with links to other resources, including a link over to the Stand Down website where you can browse through other presentations and information about that event held in late 2024.

02:11:25.000 --> 02:11:33.000
That URL is shown in red. It is active from today forward. You can also access it through the QR code shown on the right of this slide.

02:11:33.000 --> 02:11:58.000
Now, if you are watching the recorded version of today's webinar, that website is still available. So you can visit that website and access the materials. And one of the most important things on that website is our feedback form. I commonly get asked if we offer CEUs or PDHs. And while I can't issue those types of credit hours, I can give you a certificate of participation If you fill out the feedback form. So please visit the seminar homepage. Again, the URL shown in red at the top of this slide.

02:11:58.000 --> 02:12:17.000
Fill out the feedback form. If you scroll down, you'll find it. And make sure you check the box at the bottom of that feedback form certifying you are here for the entire delivery. As long as you check that box at the bottom and submit it, you'll then have access to the certificate with all of the details for the event and a link back to that homepage if you need to download information about our speakers, the materials for crediting.

02:12:17.000 --> 02:12:31.000
Purposes with your own organization. If you happen to watch the recorded version, again, you can still get to that form, fill out the feedback form based off your replay of the archived version, checking that box saying you watched the whole archive and get a certificate based on your replay.

02:12:31.000 --> 02:12:42.000
I do encourage you to download the participation certificate from the confirmation screen because sometimes the email that I send gets caught up by junk or spam filters. So fill out the form, save the certificate right from that confirmation screen.

02:12:42.000 --> 02:13:12.000
Again, that seminar homepage is available from today forward, and I hope that you found this to be a valuable expenditure of your time. We look forward to having you join us for a future internet seminar. And with that, I'll go ahead and formally conclude today's live broadcast. Thank you so very much for joining us.