Chemical Oxidation Site Profiles

Georgia Naval Submarine Base at GeoCleanse Project 49
Last Updated: November 15, 2002
Site Identifying Information                                     
Project Name, Location:   Georgia Naval Submarine Base, St. Mary's, GA
(EPA Region 4)
Site Name:   GeoCleanse Project 49
Cleanup Program:   Georgia EPD
Site Type:   Federal Facility
 
Design and Operation Factors                                

Technology Design and Operation:   Controlled In-Situ Chemical Oxidation injection, using the simultaneous injection of dilute hydrogen peroxide and a site-specific catalyst blend.
Vendor:   GeoCleanse
Oxidant Type:   Fenton's Reagent
Number of Oxidant Injections or Passes:   4 different areas
Volume of Media Treated:   158,400 cu ft groundwater treated
Concentration of Oxidant:   3 -12% concentrations of hydrogen peroxide
Date Operation Began:   November 1998
Date Operation Was/Will be Complete:   January 2002
Summary and Description of Performance Data:   Site performance monitoring included daily groundwater monitoring and offgas analysis. Parameters measured in the field included pH, peroxide, chloride, iron, alkalinity, Carbon Dioxide and headspace analysis. Laboratory analytical data was performed on samples collected upon completion of the injection program and indicated an average reduction of 94% across the site and also achieving the clean up goal of < 100 ug/L.
 
Project Data Elements                                              
Last Update of Database:   November 15, 2002
Project Scale:   Full Scale
Project status:   Complete
Contaminants of Concern:  
Chemical Name Conc. Units Comments
1,1-Dichloroethene
Tetrachloroethene
Vinyl chloride
Trichloroethene
Halogenated VOCs
Extent/size of area of contamination:   158,400 cu ft groundwater treated
Presence of naturally occuring carbon?   No
Geologic Setting:   Fine sand, silt and clay
Geology and hydrogeology detailed description:   Surface to 48 ft bgs fine sands and silts
Media type:   Soil
Groundwater
Cleanup goals or remedial objectives:   Reduce alphaiatics to <100µg/L
Are Performance Data Available?   No
 
Contact Information                                                   
Contact:   Dan Bryant
Geo-Cleanse International
Matawan  New Jersey  
Information Source:   Bryant, D. "A Novel Combined Oxidant In-Situ Remediation Approach for Brownfield Redevelopment Linked to Construction of a “Green” Power Plant". 8th International Conference Remediation of Chlorinated and Recalcitrant Compounds. May 21-24, 2012.